MMC Cost Catalogue

MMC-VC — 1×1 Cost

1 leg · 1 level · M

Single-leg, single-deck viaduct carrying maglev passenger only at 600 km/h. The Phase 0-2 Newcastle–Sydney ridge route runs on MMC-VC.

Configuration
Single-leg, single-deck
Service levels
One
Pylon spacing
25 m
Foundation baseline
10 m

Structure, Services, Install — total.

Per-kilometre cost is split into three layers: Structure (the bare elevated platform — foundation, pylon, cap beam, deck, walkway), Services (service-specific equipment installed on the structure), and Install (all field labour and plant). Total per km is the sum of the three. The service items themselves (water, conductors, fibre cable, track, maglev hardware) are catalogued separately on the relevant Service pages and added to deployment cost. Per-km basis: 25 m pylon spacing (40 pylons/km).

Structure

The bare elevated platform — foundation, pylon, transverse cap beam(s), longitudinal girders, deck modules, and permanent equipment (walkway, handrails). Module costs are Megafactory pour rate + Hub and die allocation at moderate platform utilisation (~$310/module). Pre-feasibility grade, ±30%.

Item Per pylon / span (AUD) Per-km (AUD)
Cutter head (sacrificial hybrid) $10,000 / pylon $400,000
Caisson ring segments (precast concrete) — 4 m OD, 300 mm wall, C65, 10 rings at 10 m depth $6,850 / pylon $274,000
Caisson anchor cap (precast concrete) — 4 m OD annular, 1 per caisson $935 / pylon $37,400
Pressure grout — annular grouting, rock socket bond (~1.5 m³/caisson) $600 / pylon $24,000
Tubular tension element — 13.375″ × 72 ppf L80 13Cr API 5CT, ~12 m $5,400 / pylon $216,000
Pylon column segments (precast concrete) — tapered P#7, 3 segments typical $2,280 / pylon $91,200
HB1 transverse cap beam — single-leg ~10 m wide, 17 t $1,210 / pylon $48,400
Pylon head / cap $695 / pylon $27,800
HB2 maglev longitudinal girders (25 m, 3 per span) $3,930 / span $157,200
Walkway, handrails, fall protection $5,000 / span $200,000
Structure subtotal $1,476,000

Services

Service-specific equipment installed on the structure to enable the services it carries (saddles, brackets, conduits, guideway supports). The service items themselves — track, conductors, water pipe, fibre cable, maglev hardware — are catalogued separately on the relevant Service pages and added to deployment cost.

Item Per span (AUD) Per-km (AUD)
Maglev guideway base / saddles (structure-mounted) $2,500 / span $100,000
Fibre + signalling conduit $800 / span $32,000
Power feeder supports (propulsion auxiliary) $1,200 / span $48,000
Services subtotal $180,000

Install

All field labour and plant required to deploy the structure and services. Drilling rig service charged at ~$1,200/hour all-in (crew + plant + fuel). Self-building methodology compresses install cost: rig and crane work from the deck of the already-built section.

Item Per pylon / span (AUD) Per-km (AUD)
Foundation drilling service (6 hrs × $1,200, 10 m baseline) $7,200 / pylon $288,000
Pylon segment erection (3 segs + tubular + tensioning) $2,500 / pylon $100,000
HB1 cap beam placement $1,500 / pylon $60,000
QA, commissioning $800 / pylon $32,000
Girder placement (3 × $400) $1,200 / span $48,000
Maglev guideway laying $3,500 / span $140,000
Fibre + power pull $1,500 / span $60,000
Install subtotal $728,000

MMC-VC — Single-Leg Single-Deck — per kilometre

Structure + Services + Install. The service items themselves (track, conductors, water pipe, fibre cable, maglev hardware) are catalogued on their respective Service pages and added to deployment cost. Foundation costed at 10 m baseline depth; deeper foundations on river crossings or floodplain sections add cost in proportion.

Structure
$1,476,000
Services
$180,000
Install
$728,000
Single-Leg total per km
~$2.38 M

Pre-feasibility grade, ±30%. Modules costed at Megafactory pour rates from Memo 2 (Megafactory Economics) plus moderate-utilisation Hub and die allocation (~$310/module). Install rates are pre-feasibility benchmarks against light civil construction at corridor scale. All figures AUD. Detailed engineering and quantity surveying required before any binding use.

MMC-VC model page → · ← Back to the cost catalogue