MMC Cost Catalogue

MMC-TB Cost — Single-Leg Transmission

The standard single-pylon transmission tower covering approximately 80% of MMC transmission deployments — 132 kV through ±500 kV HVDC suspension. The Phase 0 corridor backbone runs on MMC-TB. Single 4 m base, single 20″ L80 13Cr tubular, standard ATS caisson.

Configuration
Single
Tower spacing
100 m
Towers per km
10
Foundation baseline
15 m

Structure, Services, Install — total.

Per-tower cost is split into three layers: Structure (foundation, pylon, tubular, cross-arm), Services (tower-mounted equipment for the transmission service), and Install (all field labour and plant). Total per tower is the sum of the three; per-km figures shown at 100 m typical transmission spacing (10 towers per kilometre). Actual deployment density varies with voltage and terrain.

Structure

Foundation, pylon column, tubular tension element, cross-arm. Module costs are Megafactory pour rate + Hub and die allocation at moderate platform utilisation (~$310/module). Pre-feasibility grade, ±30%.

Item Per tower (AUD) Per-km (AUD)
Cutter head (sacrificial hybrid) $10,000 $100,000
Caisson ring segments (precast concrete) — 4 m OD, 300 mm wall, C65, 15 rings at 15 m depth $10,275 $102,750
Caisson anchor cap (precast concrete) $935 $9,350
Pile cap / base slab (precast concrete) $935 $9,350
Pressure grout — annular grouting, rock socket bond $800 $8,000
Tubular tension element — 20″ × 171 ppf L80 13Cr API 5CT, ~17 m $12,240 $122,400
Column segments L1–L6 (precast concrete, 6 tapered) $4,560 $45,600
Cross-arm (P#7 precast + steel rib, conductor attachment hardware integrated) $1,950 $19,500
Structure subtotal $41,695 $416,950

Services

Tower-mounted equipment for the transmission service. The conductors themselves are catalogued on the HVDC Transmission service page and added to deployment cost.

Item Per tower (AUD) Per-km (AUD)
Conductor attachment hardware (insulator string sets) $3,500 $35,000
Fibre optic OPGW attachment fittings $600 $6,000
Aviation lights + earthing + bonding $1,200 $12,000
Anti-climb, signage, access $800 $8,000
Services subtotal $6,100 $61,000

Install

All field labour and plant required to deploy the tower and string the conductors. Drilling rig service charged at ~$1,200/hour all-in. Includes site access, survey, easement and permits, and project management allocation per tower.

Item Per tower (AUD) Per-km (AUD)
Foundation drilling (8 hrs × $1,200/hr, 15 m baseline) $9,600 $96,000
Pylon segment erection (6 segs + tubular + tensioning) $4,500 $45,000
Cross-arm placement $1,500 $15,000
Conductor stringing (allocated per tower) $8,000 $80,000
Earthing, OPGW, lighting install $2,000 $20,000
Site access + survey (per tower allocation) $3,000 $30,000
Easement + permits (per tower allocation) $2,500 $25,000
Project management + supervision $4,000 $40,000
QA, commissioning, energisation $1,500 $15,000
Install subtotal $36,600 $366,000

MMC-TB — Single-Leg Transmission Tower — per tower & per kilometre

Structure + Services + Install. Conductor cable itself catalogued separately on the HVDC Transmission service page; deployment cost = tower cost + conductor per-km. At 100 m typical transmission spacing this works out to 10 towers per kilometre.

Structure
$416,950 / km
Services
$61,000 / km
Install
$366,000 / km
MMC-TB per tower
$84,395
MMC-TB per km
~$0.84 M

Pre-feasibility grade, ±30%. Modules costed at Megafactory pour rates from Memo 2 (Megafactory Economics) plus moderate-utilisation Hub and die allocation (~$310/module). Install rates are pre-feasibility benchmarks against light civil construction at corridor scale. All figures AUD.

The MMC-T tension sizing memo and the MMC-TB model page state ~$138,000 per tower as the market-comparable cost (vs ~$140,000 for steel lattice equivalent). The bottoms-up build cost on this page comes in lower because it reflects the build-stage cost only. The difference represents project margin, contractor overhead, financing, and contingency applied between the build cost and the delivered price.

MMC-TB model page → · ← Back to the cost catalogue