MMC Cost Catalogue

MMC-VB — 2×2 Cost

2 legs · 2 levels · M, F, HV, HL, G, H2, FB, W

The Phase 0 corridor workhorse. Dual-leg, two-deck viaduct carrying freight at 6 m + maglev at 17 m with HVDC arms, gas, hydrogen, fibre, and water services on one structure.

Configuration
Dual-leg, two-deck
Service levels
Two
Pylon spacing
25 m
Foundation baseline
15 m

Structure, Services, Install — total.

Per-kilometre cost is split into three layers: Structure (the bare elevated platform — foundation, pylon, cap beam, deck, walkway), Services (service-specific equipment installed on the structure), and Install (all field labour and plant). Total per km is the sum of the three. The service items themselves (water, conductors, fibre cable, track, maglev hardware) are catalogued separately on the relevant Service pages and added to deployment cost. Per-km basis: 25 m pylon spacing (40 pylons/km).

Structure

The bare elevated platform — foundation, pylon, transverse cap beam(s), longitudinal girders, deck modules, and permanent equipment (walkway, handrails). Module costs are Megafactory pour rate + Hub and die allocation at moderate platform utilisation (~$310/module). Pre-feasibility grade, ±30%.

Item Per pylon / span (AUD) Per-km (AUD)
Cutter heads (sacrificial hybrid, 2 per pylon — 1 per leg) $20,000 / pylon $800,000
Caisson ring segments — 30 rings (15 per leg × 2 legs, 15 m depth) $20,550 / pylon $822,000
Caisson anchor caps (2 per pylon) $1,870 / pylon $74,800
Pressure grout (2 caissons × 1.5 m³) $2,400 / pylon $96,000
Tubulars — 2 × 20″ × 171 ppf L80 13Cr API 5CT, ~20 m each (15 m caisson + 5 m stickup) $28,800 / pylon $1,152,000
P1/P2 lower column segments (precast, 4 segments to freight at 6 m) $3,040 / pylon $121,600
HB1 transverse cap beam (17 m wide, freight + HVDC arms, 65 t) $1,950 / pylon $78,000
P3/P4 upper column segments (precast, 4 segments to maglev at 17 m) $3,040 / pylon $121,600
HB3 transverse cap beam (17 m wide, maglev level, 43 t) $1,950 / pylon $78,000
Pylon heads (2 per pylon — 1 per leg) $1,390 / pylon $55,600
XA-C HVDC arm modules (4 per pylon — bolt-on at HB1 and HB3) $3,740 / pylon $149,600
HB2 freight longitudinal girders (25 m, 5 per span) $6,550 / span $262,000
HB4 maglev longitudinal girders (25 m, 5 per span) $6,550 / span $262,000
Walkway, handrails, fall protection (dual-deck) $8,000 / span $320,000
Structure subtotal $4,393,200

Services

Service-specific equipment installed on the structure to enable the services it carries (saddles, brackets, conduits, guideway supports). The service items themselves — track, conductors, water pipe, fibre cable, maglev hardware — are catalogued separately on the relevant Service pages and added to deployment cost.

Item Per span (AUD) Per-km (AUD)
Freight track ballast + tie supports $4,500 / span $180,000
Maglev guideway saddles $3,500 / span $140,000
HVDC conductor insulator brackets $2,000 / span $80,000
Gas / hydrogen pipe support saddles $2,500 / span $100,000
Water pipe support saddles $1,800 / span $72,000
Fibre wireway + signalling conduit $1,200 / span $48,000
Power feeder supports (auxiliary) $1,000 / span $40,000
Services subtotal $660,000

Install

All field labour and plant required to deploy the structure and services. Drilling rig service charged at ~$1,200/hour all-in (crew + plant + fuel). Self-building methodology compresses install cost: rig and crane work from the deck of the already-built section.

Item Per pylon / span (AUD) Per-km (AUD)
Foundation drilling (SBC dual drilling rig, 8 hrs × 2 caissons × $1,200, 15 m) $19,200 / pylon $768,000
Pylon segment erection (8 segs both legs + 2 tubulars + tensioning) $6,000 / pylon $240,000
Cap beam placement (HB1 + HB3, 2 × $1,500) $3,000 / pylon $120,000
XA-C HVDC arm bolt-on (4 × $400) $1,600 / pylon $64,000
QA, commissioning $1,500 / pylon $60,000
Girder placement (10 girders × $400) $4,000 / span $160,000
Freight track laying $8,000 / span $320,000
Maglev guideway laying $3,500 / span $140,000
HVDC conductor stringing + insulators $3,000 / span $120,000
Pipe runs (gas, hydrogen, water) $4,000 / span $160,000
Fibre + power pull $1,500 / span $60,000
Install subtotal $2,212,000

MMC-VB — Two-Level Dual-Leg — per kilometre

Structure + Services + Install. The service items themselves (track, conductors, water pipe, fibre cable, maglev hardware) are catalogued on their respective Service pages and added to deployment cost. Foundation costed at 15 m baseline depth; deeper foundations on river crossings or floodplain sections add cost in proportion.

Structure
$4,393,200
Services
$660,000
Install
$2,212,000
Two-Level Dual-Leg total per km
~$7.27 M

Pre-feasibility grade, ±30%. Modules costed at Megafactory pour rates from Memo 2 (Megafactory Economics) plus moderate-utilisation Hub and die allocation (~$310/module). Install rates are pre-feasibility benchmarks against light civil construction at corridor scale. All figures AUD. Detailed engineering and quantity surveying required before any binding use.