Transmission Model — Standard Single-Leg

MMC-TB — single-leg standard transmission.

The standard single-pylon transmission tower. 4m OD base, 1m OD top, tapered concrete pylon held in compression by a single 20" L80 13Cr API 5CT tubular tensioned against a standard ATS caisson at foundation depth. Covers approximately 80% of every transmission tower in the deployment range as a stand-alone single pylon. The Phase 0 corridor's ±500kV HVDC backbone is built entirely on MMC-TB.

MMC-TB at a glance.

ConfigurationSingle-leg, cross-arm topside
Legs per pylon1
Base diameter4.0 m OD at the base (the caisson width), tapering to 2.5 m OD at the top; detailed design needed
Wall thickness300 mm at the base, tapering 100 mm per 99 m of height (~190 mm at 54 m)
Concrete gradeC65 precast (65 MPa characteristic strength)
Typical pylon height50–60m (standard 330kV through ±500kV); height varies by application
Design option: second cross-armA second cross-arm is captured between two pylon joints higher up the single leg, for a second circuit or bipole. Both arms are clamped between segments by the tubular tension. Spacing and height: detailed design.
Foundation1 × 4m OD ATS caisson — drilled-and-grouted, depth per geology (typically 8–18m in NSW corridor). At the 10 m planning depth: 5 ring segments of 2 m + caisson head, ~122 t. Depth depends on soil, rock and load, and is confirmed by geotechnical study.
Tubular1 × 20" × 171ppf L80 13Cr API 5CT — body yield 17.2 MN, joint yield 16.4 MN (premium connection)
Voltage range covered22kV distribution through ±500kV HVDC — approximately 80% of the network
Worked PT requirements22kV distribution: 1.0 MN · 132kV suspension: 4.2 MN · 132kV strain: 9.6 MN · 330kV AC suspension: 11.3 MN (69% utilisation) · 500kV AC suspension: 15.9 MN (at hard ceiling) · ±500kV HVDC bipole: 14.9 MN. (Tension figures are for the earlier 4.0 → 1.0 m taper; recalculation for the 4 m to 2.5 m taper is left to detailed design.)
Concrete mass per tower~317 tonnes of pylon joints for a 55 m tower (4 m base to 2.5 m top), plus ~122 t of caisson (Megafactory cast-skin manufacture). The earlier ~210 t was for a 4.0 → 1.0 m taper; see the bill of materials.
All-in cost per tower (volume)~$170,000 (vs ~$140,000 for steel lattice equivalent). The 4 m to 2.5 m pylon joint adds ~107 t of concrete at ~$300/t (~$32,000) to the earlier ~$138,000. See the bill of materials. Pricing is under full review: Economics →
60-year lifecycle NPV~$187,000 per tower (vs ~$295,000 steel lattice — ~37% lifecycle saving; was ~$155,000 and 47%)
Installation1–2 days per tower, 4–6 person crew, single crane day (vs 5–10 days, 8–15 crew, 3–5 crane days for steel lattice)
MMC-DWG-002-04 MMC-TB Transmission — summary drawing
MMC-DWG-002-04 · MMC-TB Transmission. Single-leg tower with a captured cross-arm; option: a second cross-arm. Summary sheet, Rev D. Select to enlarge.
MMC-DWG-005-04 MMC-TB bill of materials — every part pointed out, with quantities per tower and per km
MMC-DWG-005-04 · MMC-TB Bill of Materials. The build from the standard MMC parts: every part numbered, with quantity and mass per tower and per km. Rev F. Select to enlarge.

See this design built from standard modular components, with every part and the quantities per km →

How MMC-TB is built on the platform.

MMC-TB is the single SKU that covers the bulk of continental transmission deployment. Same 4m base, same 20" L80 13Cr tubular, same ATS caisson — across distribution, sub-transmission, transmission, and HVDC bipole applications. Only the height, cross-arm configuration, and conductor attachment hardware vary per voltage class.

The cross-arms are captured between pylon segments and held in place by the tensioned tubular passing through them. They carry conductors for transmission applications (one cross-arm per circuit, three to four arms typical). The cross-arm hub geometry is patented (Patent 5) and allows mix-and-match arm fitment per project. The renewable tubular tension element (Patent 4) means the structural tubular can be inspected, retensioned, or replaced across the 80-year design life — extending operational life beyond what conventional embedded-rebar concrete can deliver.

Where MMC-TB is deployed.

MMC-TB is deployed across the entire MMA transmission network as the default single-pylon configuration. Phase 0 corridor's ±500kV HVDC backbone is entirely MMC-TB (suspension towers; MMC-TA at strain points). Phase 1, 2, and 3 continental corridors deploy MMC-TB across most suspension towers up to ±500kV HVDC.

MMC-TB is the workhorse of the MMA transmission deployment. Phase 0 corridor uses MMC-TB exclusively for the HVDC backbone suspension towers. International deployments will follow the same single-product approach.

Phase 0 Phase 0 ±500kV HVDC backbone. Suspension towers MMC-TB throughout. ~96,000 transmission tower locations across 2,400km.

Companion documents.

The engineering of MMC-TB is documented in the MMC memo series. The Models page is the catalogue — the Library is the engineering depth.

Memo 2 MMC-T Transmission Tower Tension Sizing. Worked example — 330kV AC suspension tower (the most common case). Full tension calculation, tubular selection, lifecycle NPV vs steel lattice. Covers MMC-TB across the full deployment range.
Memo 3 Foundation Anchor Architecture. Standard 4m ATS caisson — same foundation deployed across all MMC-TB pylons.

MMC-TB on the MMC Patent Family.

MMC-TB is the canonical single-pylon configuration covered by the Pole and Tower Architecture (Patent 6). The foundation system (Patents 1, 2, 3 — Foundation Core, Integrated Foundation, Foundation Drilling System), the Architectural Framework (Patent 4 — modular precast segments, renewable tension element), and the Manufacturing Architecture (Patent 7 — cast skin / rib / die assembly-line manufacture) all apply to MMC-TB. The conductor cross-arm capture geometry is covered by Patent 5.

View the MMC Patent Family →