MMC Cost Catalogue

MMC-TA Cost — Dual-Leg Transmission

Two standard MMC pylons spaced 12–15 m apart, structurally coupled by three captured cross-beams. High-voltage strain towers, river crossings, and heavy conductor loading up to ±1100 kV UHVDC. Used as intermittent strain towers along an otherwise-TB line.

Configuration
Dual
Tower spacing
100 m
Towers per km
10
Foundation baseline
15 m

Structure, Services, Install — total.

Per-tower cost is split into three layers: Structure (foundation, pylon, tubular, cross-arm), Services (tower-mounted equipment for the transmission service), and Install (all field labour and plant). Total per tower is the sum of the three; per-km figures shown at 100 m typical transmission spacing (10 towers per kilometre). Actual deployment density varies with voltage and terrain.

Structure

Foundation, pylon column, tubular tension element, cross-arm, and captured cross-beams. Module costs are Megafactory pour rate + Hub and die allocation at moderate platform utilisation (~$310/module). Pre-feasibility grade, ±30%.

Item Per tower (AUD) Per-km (AUD)
Cutter heads (sacrificial hybrid, 2 per tower — 1 per leg) $20,000 $200,000
Caisson ring segments (precast concrete) — 30 rings (15 per leg × 2 legs, 15 m depth) $20,550 $205,500
Caisson anchor caps (2 per tower) $1,870 $18,700
Pile caps / base slabs (2 per tower) $1,870 $18,700
Pressure grout (2 caissons × 2 m³) $1,600 $16,000
Tubulars — 2 × 20″ × 171 ppf L80 13Cr API 5CT, ~17 m each $24,480 $244,800
Column segments (precast concrete, 12 tapered — 6 per leg) $9,120 $91,200
Captured cross-beam modules (3 × complex P#7 + steel rib) $5,850 $58,500
Cross-beam-to-column saddle hardware (6 saddles) $2,400 $24,000
Structure subtotal $87,740 $877,400

Services

Tower-mounted equipment for the transmission service. The conductors themselves are catalogued on the HVDC Transmission service page and added to deployment cost.

Item Per tower (AUD) Per-km (AUD)
Conductor attachment hardware (3 bipoles × insulator string sets) $7,500 $75,000
Fibre optic OPGW attachment fittings $800 $8,000
Aviation lights + earthing + bonding $2,000 $20,000
Anti-climb, signage, access $1,500 $15,000
Services subtotal $11,800 $118,000

Install

All field labour and plant required to deploy the tower and string the conductors. Drilling rig service charged at ~$1,200/hour all-in. Includes site access, survey, easement and permits, and project management allocation per tower.

Item Per tower (AUD) Per-km (AUD)
Foundation drilling (SBC dual rig, 8 hrs × 2 caissons × $1,200) $19,200 $192,000
Pylon segment erection (12 segs both legs + 2 tubulars + tensioning) $8,500 $85,000
Cross-beam placement (3 captured beams) $5,000 $50,000
Conductor stringing (3 bipoles allocated) $15,000 $150,000
Earthing, OPGW, lighting install $3,500 $35,000
Site access + survey $4,000 $40,000
Easement + permits $4,000 $40,000
Project management + supervision $6,000 $60,000
QA, commissioning, energisation $3,000 $30,000
Install subtotal $68,200 $682,000

MMC-TA — Dual-Leg Transmission Tower — per tower & per kilometre

Structure + Services + Install. Conductor cable itself catalogued separately on the HVDC Transmission service page; deployment cost = tower cost + conductor per-km. At 100 m typical transmission spacing this works out to 10 towers per kilometre.

Structure
$877,400 / km
Services
$118,000 / km
Install
$682,000 / km
MMC-TA per tower
$167,740
MMC-TA per km
~$1.68 M

Pre-feasibility grade, ±30%. Modules costed at Megafactory pour rates from Memo 2 (Megafactory Economics) plus moderate-utilisation Hub and die allocation (~$310/module). Install rates are pre-feasibility benchmarks against light civil construction at corridor scale. All figures AUD.

MMC-TA is a strain tower deployed intermittently along an otherwise-TB line — typically every few kilometres or at terrain crossings. The per-km cost shown at 100 m spacing is the catalogue reference rate for direct comparison; actual deployment density is much lower, so the effective contribution to total corridor cost is correspondingly smaller.

MMC-TA model page → · ← Back to the cost catalogue