Models · Modular Components · MMC-TB Guyed

MMC-TB Guyed: built from standard modular components.

The standard tower plus three guys to ground anchors, for ±500 kV HVDC strain without a second leg. Every part is a standard MMC part, made on the same line as every other model. The sheet points to each one; the table counts them per tower and per km.

Every part, pointed out.

Numbers 1–10 are the structural parts; letters are the services this build carries. Details 1 and 2 enlarge the foundation and the top of a leg. Select the sheet to open it full size.

MMC-DWG-005-05 MMC-TB Guyed modular components — the build with every part pointed out

The parts list.

5 towers per km (200 m apart). Numbers match the callouts on the sheet.

No.PartPer towerPer kmMass per tower
11A5Anot set
21A5Anot set
35A25A~113.1 tA
41A5A~8.8 tA
56A30A~16.5 tA
618A90A~317.4 tA
71A5Anot set
81A5Anot set
915not set
10315not set
Concrete in parts with a set mass~2,200 tA~439 tA
Tubular steel~80 tA~16.5 tA
Mass not yet set: cutter head, anchor latch, pylon cap, tension lock, captured cross-arm, guy wires and ground anchors

Expansion packers and centralisers are fitted as each foundation needs and are not counted per km.

Services this build carries.

Each service adds its own parts on the same structure. Per km of corridor.

Ref.Service partPer km
A
Insulators and conductors
Per circuit as designed for the voltage (22 kV to ±500 kV on TB; to ±1100 kV on TA). Not counted here.

Service letters on the page list every service; the sheet letters only those drawn.

Assumptions.

Unmarked figures are the model page's own, multiplied out. Values marked A rest on:

  1. Towers 200 m apart, so 5 per km (ruling 10 Nov 2026). For comparison, Australian 330 kV and 500 kV lines run 300–600 m (Transgrid, EnergyCo, Energy Safe Victoria).
  2. Tower height 55 m; caisson 10 m planning depth (MMC-TB gives 8–18 m by geology).
  3. MMC-TB: pylon cap and tension lock, one per leg. MMC-TA: one cross-beam across the pylon tops in place of the caps; one tension lock per leg, on the beam.
  4. Pylon joints ~3 m (from MMC-VC: 2 segments for 6 m); counts are worked out from the heights on the 002 sheets.
  5. Tension tubular per leg = caisson depth + height to the top of the structure, in whole ~12 m sections (12 m confirmed by Brett, 9 Nov 2026).
  6. Caisson rings are 2.0 m tall (ruling 9 Nov 2026). Rings per caisson = planning depth ÷ 2, rounded up: VC 10 m → 5, VB 15 m → 8, VA 20 m → 10, VD 20 m → 10 (depth assumed as VA), towers 10 m → 5. Caisson depth depends on soil, rock and load and is confirmed by geotechnical study, so every ring count is provisional.
  7. Services per span (dead load only, no trains): freight rail 3 tracks × 2 rails × 25 m at 60 kg/m = ~9 t; HVDC 8 poles × 6 sub-conductors × 25 m at ~2.5 kg/m = ~3 t; gas pipe 750 mm, 15.9 mm wall = ~7 t; water pipe 1 m, 12 mm wall = ~8 t and its water ~20 t (VB); fibre ~1 t. VA water: full-bay channel 6.4 m deep × 16.4 m wide × 25 m = ~2,624 t (replaces the published 4,250 t). VA channel wall panels: size, number and mass to detailed design, not included in the dead load.
  8. Masses from geometry, reinforced concrete at 2.5 t/m³. Caisson ring 4.0 m OD, 0.4 m wall, 2.0 m tall: ~22.6 t. Caisson head 4.0 m OD, 1 m hole, 0.3 m thick: ~8.8 t. Teeth and grout not included.
  9. Pylon joints (ruling 10 Nov 2026): ~3 m each; every pylon 4.0 m outside diameter at the base (the caisson width) tapering to 2.5 m at its top, whatever its height. Wall taken as 300 mm at the base, thinning 100 mm per 99 m. Masses are estimated on that taper; detailed design is needed.
  10. Tubular: 20 in × 171 ppf = ~254 kg/m (VC: 13-3/8 in × 72 ppf = ~107 kg/m), per the model pages.
  11. Cross beams: memo masses. VC HB1 ~17 t; VB HB1 ~43 t, HB3 ~29 t; VA HB1–HB5 ~65, 65, 43, 43 and 29 t (Big Bertha memo); VD by analogy ~43 (freight), ~43 (services deck, as VA HB3) and ~29 t (maglev), assumed. Transmission cross-arms and cross-beams: not set.
  12. Longitudinal beams: estimate on Super-T proportions (1,000 mm deep for spans to 25 m; 100 mm webs; 240 mm base), widened to a flush 3.4 m unit: 180 mm top flange forming the deck, two 100 mm webs, a 1.2 m × 240 mm bottom flange, 1 m solid at each end: ~1.08 m² of concrete, ~72 t per 25 m beam. VA aqueduct level taken the same (its load is heavier; not yet sized).
  13. Cutter head: cast high-alloy steel with bit inserts; mass is not a design driver and is left to detailed design.

MMC-TB Guyed specification →   All parts →