MMC-VB and MMC-VC Viaduct Engineering

Pylon geometry, cap beam and girder design, HVDC arm loading, longitudinal wire-rope continuity system.

Memo6 — Viaduct Engineering
AuthorBrett Murrell
Versionv1.0
Date6 May 2026
PatentsAU 2026904069 (P#4), AU 2026904075 (P#5)
Word count~6,600
The MMC-VB and MMC-VC viaduct configurations share a common architectural pattern: dual-leg or single-leg precast concrete pylons supporting one or two decks of integrated service infrastructure across 25 m spans. This memo describes the pylon geometry, the cap beam and longitudinal girder design, the HVDC arm loading (broken-wire load case governs), and the longitudinal wire-rope continuity system that ties pylons together along the corridor. The two-stage construction methodology — Stage 1 freight viaduct commissioned first, Stage 2 upper structure built on the running freight line — is detailed for both MMC-VB (Phase 0 standard) and MMC-VC (urban passenger).
25 mStandard span
2 stagesFreight first, upper structure on running line
HVDC broken wireGoverning load case
P#8 candidateWire-rope continuity flagged

MEMO 6 — MMC-VB AND MMC-VC VIADUCT ENGINEERING — PRE-FEASIBILITY — INTERNAL WORKING DOCUMENT

SOVEREIGN BUILD CORPORATION

Memo 6 — MMC Viaduct Engineering

MMC-VB and MMC-VC Pylon Spec — Pre-Feasibility Structural Model

Dual-leg two-level viaduct for Phase 0 (Melbourne–Brisbane) and single-leg single-deck viaduct for Phase 0.2 (Newcastle–Sydney Direct). Both built from the same 4m standard foundation and the same MMC pylon segment family.

Pylon B span wt (concrete) ~865t MMC-VB dual-leg, two-level — Phase 0 Pylon C span wt (standard) ~347t MMC-VC single-leg, single-deck — Phase 0.2 Shared foundation 4m OD Same caisson, same segments, same rig Shared pylon family 3m segs Same tapered column — stacks to 100m+

Brett Murrell — Inventor & Candidate, Robertson

May 2026 — INTERNAL WORKING DOCUMENT — PRE-FEASIBILITY GRADE

1. Introduction — One Platform, Two Configurations

The MMC structural platform is defined by a fixed set of architectural primitives — foundation, pylon segments, cap beams, and longitudinal girders — that combine in different configurations to produce every deployment type. This memo models two specific configurations at pre-feasibility grade:

Pylon B — MMC-VB Pylon C — MMC-VC
Programme Phase 0 — Melbourne to Brisbane Phase 0.2 — Newcastle to Sydney Direct
Configuration Dual-leg, two-level viaduct Single-leg, single-deck viaduct
Legs per pylon 2 (left + right) 1
Decks Stage 1 freight at 6m + Stage 2 maglev at 17m Single maglev deck — height varies with terrain
Services 10+ — freight, maglev, HVDC, gas, fibre, water Maglev passenger only — 600km/h
Corridor 2,423km inland spine 133.2km Newcastle → Sydney direct
Pylons (Phase) 96,920 pylons Phase 0 5,328 pylons Phase 0.2
Foundation Standard 4m OD caisson — 2 per pylon Standard 4m OD caisson — 1 per pylon
Tubulars 2 × 20" × 171ppf L80 13Cr (one per leg) 1 × 13.375" × 72ppf L80 13Cr — reduced for handling at height
Both configurations are built from the same Newcastle Megafactory. The foundation caisson, the ring segments, the pylon column family, the cap beams, and the longitudinal girders are identical production units. The configuration is determined by how many legs are erected and how many deck levels are built — not by different module types. This is the architectural principle that makes the Megafactory economics work.

2. Shared Foundation — The Standard 4m Caisson

Both Pylon B and Pylon C use the identical foundation system. The 4m OD caisson is the standard MMC foundation — drilled by the same rig, assembled from the same ring segment family, anchored by the same cutter head. The only difference is quantity: Pylon B requires two caissons per pylon location (one per leg); Pylon C requires one.

FOUNDATION — STANDARD 4m CAISSON (per leg)
Parameter Specification Notes
Caisson outer diameter 4.0m OD Standard MMC caisson — applies to both Pylon B and Pylon C
Wall thickness 300mm C65 precast, P#7 skin/rib/die manufacture
Design depth (planning) 15m Geology-dependent — range 5m to 20m+ in hard rock
Ring segment height 1.0m per ring Design variable — 1m to 2m options; 1m is planning assumption
Ring segments per leg 15 (at 1m rings, 15m depth) Full ring = 1 module; all identical from same production line
Ring segment weight ~8.4t each 4m OD × 300mm wall × 1m high — C65 concrete
Caisson head / anchor cap 1 per leg ~8.5t — annular donut, 4m OD × 1m ID × 0.3m high. Lid on caisson. Pylon column sits on top. Tubular passes through centre bore.
Cutter head (hybrid) 1 per leg — stays in ground Steel/concrete hybrid — drilling tool + permanent PT anchor
Tubular — Pylon B (Phase 0) 20" × 171 ppf L80 13Cr API 5CT One per leg — 2 per pylon. Heavy-load dual-leg platform justifies this size. Phase 0 procurement at scale.
Tubular — Pylon C (Phase 0.2) 13.375" × 72 ppf L80 13Cr API 5CT One per pylon. Structurally adequate at all Phase 0.2 heights (7.0 MN joint capacity vs near-zero demand). Reduces joint weight from 2.35t to 1.26t — significantly better handling on narrow single-leg platform at height.
Joint capacity 16.4 MN at premium connection 95% body yield — pre-feasibility grade
Foundation weight per leg ~135t (concrete) 15 rings × 8.4t + 8.5t caisson head = ~135t (no pile cap)
Foundation — Pylon B (2 legs) ~270t Two caissons per pylon location
Foundation — Pylon C (1 leg) ~135t One caisson per pylon location

Tubular sizing note: Pylon B uses 20" × 171ppf L80 13Cr (2.35t per 12m joint) — load demands and dual-leg platform justify this size. Pylon C (Phase 0.2) uses 13.375" × 72ppf L80 13Cr (1.26t per 12m joint) — structurally adequate at all Phase 0.2 heights (7.0 MN joint capacity vs near-zero tension demand) and significantly better handling on a narrow single-leg elevated work platform. The handling argument is decisive for Phase 0.2: installing 2.35t joints on a single-leg platform at 30-70m is a major rigging operation; 1.26t joints are manageable with standard pipe-handling equipment. Both grades are L80 13Cr API 5CT — same material specification, different wall thickness.

Tubular path — Pylon B: Cutter head (foundation depth) → Caisson rings → Caisson head → P1/P2 lower columns → HB1 cap beam → P3/P4 upper columns → HB3 cap beam → Pylon head (tensioned here). The tubular runs the full height of the structure in a single continuous element — one anchor at the bottom, one tension point at the top. HB1 has upper column connection plates cast in via the rib, allowing P3/P4 to bolt on top. Pylon C omits P3/P4, HB3, HB4 — tubular runs from cutter head directly to pylon head at top of P1 stack.

Foundation depth is the single largest design variable. Geology along the Phase 0 inland corridor is predominantly alluvial and sedimentary — likely 5–10m adequate at most locations. Hard rock sections and river crossings may require 15–20m+. The ring segment count scales directly with depth: each additional metre of depth = one additional ring segment per leg. The Megafactory produces rings at the same rate regardless of depth specification.

3. Pylon B — MMC-VB Dual-Leg Two-Level Viaduct

Pylon B is the Phase 0 standard — the dual-leg two-level viaduct that carries ten integrated services along the Melbourne to Brisbane inland spine. Two parallel pylon legs, spaced 8m centre-to-centre (inside), with a 17m total corridor width. Stage 1 builds the freight deck at 6m; Stage 2 adds the maglev deck at 17m above ground.

MMC-VB dual-leg two-level viaduct — Phase 0 standard configuration. Two legs, two decks, gold HVDC arm brackets. SketchUp pre-feasibility model — not to final engineering specification.

3.1 Pylon B Geometry

Parameter Specification
Legs per pylon 2 — left leg and right leg
Leg spacing 8.0m centre-to-centre (inside); 17m total corridor width including overhang
Stage 1 freight deck height 6.0m above finished ground level
Stage 2 maglev deck height 17.0m above finished ground level
Span 25m — standard across all MMC configurations
Pylon family Tapered precast concrete — same segment family as Pylon C
Corridor width ~17m — freight + maglev + HVDC arms + services
HVDC arm bracket positions Cast into HB1 and HB3 cap beams via rib

3.2 Stage 1 — Freight Viaduct (Deck at 6m)

Component Qty/pylon Dimensions Weight Notes
P1/P2 lower col. segment 4 (2/leg × 2 legs) 4.0m OD base → 3.0m OD top, 3.0m high ~21.7t each Tapered family — 33 individual die profiles. Same 3m piece stacks to 100m for terrain crossings.
HB1 transverse cap beam 1 per pylon 17.0m wide × 1.2m deep × 1.0m thick ~43t Spans between two legs at 6m height. HVDC arm sockets + upper column connection plates cast in via rib.
HB2 longitudinal girder 5 per span 25.0m span, Super-T profile, 0.42m² cross-section, 10.5m³ concrete ~25t each = ~126t total (incl rebar/PT) Freight deck. Pandrol e-clip rail fixing inserts cast in via rib at factory precision. 1.06t/m — single crane lift at 31% of 80t rail crane capacity. Hub or Spoke.
STAGE 1 CONCRETE TOTAL ~206t/span 4 columns + HB1 + 5×HB2 girders

3.3 Stage 2 — Upper Structure (Maglev Deck at 17m)

Stage 2 is built on the commissioned freight corridor — the rail crane operates on the running freight deck, lifting upper structure components from flatbed rail wagons. The freight corridor funds and supplies its own upper-level construction.

Component Qty/pylon Dimensions Weight Notes
P3/P4 upper col. segment 4 (2/leg × 2 legs) 2.0m OD base → 1.5m OD top, 4.0m high ~9.3t each Smaller upper column family. 2 segments × 2 legs = 8m total height from HB1 top to HB3 base.
HB3 transverse cap beam 1 per pylon 17.0m wide × 1.0m deep × 0.8m thick ~29t Upper cap beam — same width as HB1. Sits on P3/P4 tops; carries HB4 maglev girders.
HB4 longitudinal girder 5 per span 25.0m span, Super-T profile, 0.40m² cross-section, 10.0m³ concrete ~24t each = ~120t total (incl rebar/PT) Maglev deck. Precision maglev guideway seats cast in via rib. 1.01t/m — single crane lift. Hub or Spoke.
Pylon head / cap 2 per pylon (top of each leg stack) 1.5m OD × 0.5m ID × 0.5m ~1.9t each = ~3.8t Top of P3/P4 stack. Tubular anchors and tensions here against cutter head at foundation depth. Tensioning hardware cast in via rib.
STAGE 2 + PYLON HEAD TOTAL ~190t/span Upper columns + HB3 + 5×HB4 girders + pylon heads

3.4 Pylon B Weight Summary

Element Concrete weight % of concrete total Notes
Foundation — 2 legs ~270t 39% 15 rings × 8.4t + 8.5t caisson head × 2 legs (no pile cap)
Stage 1 — freight viaduct ~206t 30% 4 columns (P1/P2) + HB1 + 5×HB2 girders
Stage 2 — upper structure ~190t 28% 4 columns (P3/P4) + HB3 + 5×HB4 + 2 pylon heads
CONCRETE TOTAL ~666t/span 100% All precast concrete modules combined
Non-concrete elements (est.) ~914t/span Steel tubulars ~200t, HVDC arms ~200t, rail ~100t, services ~414t
TOTAL SPAN WEIGHT ~1,580t Matches working document locked figure ✓

The non-concrete elements account for approximately 45% of total span weight. The two 20" L80 13Cr tubulars alone contribute ~200t (each tubular runs the full height — foundation depth + pylon height ≈ 30-35m at ~6t/m). HVDC arms, cross-bracing, rail, track, and services make up the remainder.

3.5 HVDC Transmission Loading — MMC-VB

MMC-VB carries four HVDC bipole circuits — 72GW total at ±800kV ultra-high voltage. The HVDC arms are steel fabrications with sockets cast into HB1 (and HB3 for upper circuits) via the P#7 rib at factory precision. The arm loads transfer directly into the cap beams and thence into the pylon legs via the tubular tension element. HVDC loading must be considered alongside structural dead and live loads in the HB1 cap beam and arm socket design.

HVDC parameter Value Notes
System voltage ±800kV HVDC Ultra-high voltage — standard for continental corridors
Total corridor capacity 72GW 4 bipole circuits per MMC-VB corridor
Circuits per corridor 4 bipole (8 poles total) Each bipole = 2 poles (+ and -)
Current per pole ~11.2 kA At ±800kV, 18GW per circuit
Conductor bundle 6 × 630mm² ACSR per pole Standard UHV HVDC bundle configuration
Bundle mass ~11.1 kg/m per pole 8 poles × 11.1 kg/m = 88.8 kg/m total
HVDC arm length ~4m each side of pylon centreline Steel fabrication — socket cast into HB1 via P#7 rib
Arm attachment points HB1 and HB3 cap beams HVDC arm sockets are P#7 rib cast-in items — factory precision
Load type Value Design case Impact on structure
Conductor dead load (8 poles) ~2.2t Permanent — all spans Vertical load on HVDC arms → HB1 bending
Insulator strings (8 poles) ~1.2t Permanent Vertical on arms
HVDC arm self-weight (8 poles) ~12.8t Permanent Vertical moment at arm-to-HB1 connection
TOTAL HVDC dead load ~16t per span Included in non-concrete 58% ~1% of total 1,580t span weight
Wind on conductors (V500) ~33.5kN lateral V500 = 48m/s Torsion in HB1 cap beam
Wind on HVDC arms ~32.5kN lateral V500 = 48m/s Torsion at arm-to-HB1 connection
TOTAL wind lateral (HVDC) ~66kN Governs HB1 torsion design Combined with pylon wind loading
Broken wire longitudinal ~420kN per pole CRITICAL CASE — one pole failure Governs arm socket and HB1 longitudinal design
The broken wire longitudinal load of ~420kN per pole is the governing design case for the HVDC arm-to-HB1 connection. When a single conductor bundle fails, the unbalanced tension pulls the arm longitudinally at full bundle tension. The P#7 rib cast-in arm socket must resist this load without yielding at the concrete-to-steel interface — this is a key structural detail requiring FEA at detailed design stage. The tubular tension element (20" L80 13Cr, 13.1 MN capacity) absorbs the resulting load path into the foundation without issue — 420kN = 0.42 MN, well within capacity.

3.6 Pylon B Module Count — Phase 0

Module Qty/pylon Phase 0 total (96,920 pylons) Hub or Spoke
Cutter head (hybrid steel/concrete) 2 193,840 Hub ONLY — special hybrid steel/concrete fabrication. Precision embedded cutting geometry, anchor receptacle, thrust bearing seat. Cannot be produced at a Spoke.
Caisson ring segment (4m OD, 1m) 30 (15/leg × 2) 2,907,600 Hub or Spoke — simplest module. High-volume hollow ring. Ideal for Spoke injection with local concrete.
Caisson head / anchor cap 2 193,840 Hub or Spoke — precision pockets cast in via rib. Spoke-producible with rebar-rib option.
P1/P2 lower col. segment (3m) 4 387,680 Hub or Spoke — 33-die tapered family. Hub preferred for quality; Spoke viable for standard runs.
HB1 transverse cap beam (17m) 1 96,920 Hub or Spoke — HVDC arm sockets and connection plates cast in via rib. Rebar-rib option enables Spoke.
HB2 longitudinal girder (25m) 5 484,600 Hub or Spoke — Pandrol fixings cast in via rib. 25t, 1.06t/m. Single crane lift. Ideal Spoke candidate.
P3/P4 upper col. segment (4m) 4 387,680 Hub or Spoke — smaller upper column. Same tapered family. Spoke-producible.
HB3 transverse cap beam (17m) 1 96,920 Hub or Spoke — same geometry as HB1 without HVDC sockets. Spoke-producible.
HB4 longitudinal girder (25m) 5 484,600 Hub or Spoke — maglev guideway seats cast in via rib. 24t, 1.01t/m. Single crane lift.
Pylon head / cap 2 (1 per leg) 193,840 Hub or Spoke — ~1.9t. Top of P3/P4 stack. Tubular tensioned here.
XA-C viaduct arm (4m bolt-on, per side) 2 per level × 2 levels = 4 387,680 Hub or Spoke — bolt-on to outer face of standard column segment at HB1 and HB3 levels. Bolt sockets cast into column face via P#7 rib — no saddle segment required.
TOTAL (incl. arm modules) ~60 ~5,815,360 Hub ONLY: cutter head only. All others: Hub or Spoke.

4. Pylon C — MMC-VC Single-Leg Single-Deck Viaduct

Pylon C is the Phase 0.2 configuration — the simplest MMC structural form. One leg per pylon, one deck level. Same foundation caisson, same pylon segment family, same Megafactory. The single-leg configuration reduces the per-pylon concrete weight by approximately 60% compared to Pylon B at standard height, and the variable-height capability means the same pylon serves both flat plains (6m) and deep valley crossings (70m+) with the same production unit.

MMC viaduct configuration family. Pylon C (Phase 0.2) is the Single Leg Single-Deck configuration (far left) — one caisson, one column, one cap beam, three girders. Pylon B (Phase 0 MMC-VB) is the Dual Leg 2-Deck configuration (third from left) — two caissons, two column stacks, freight deck at 6m and maglev deck at 17m. HB1 cap beam shown in green; deck girders and elements in pink. All configurations share the same foundation, segment, and cap beam production catalogue.

4.1 Pylon C Geometry

Parameter Specification
Legs per pylon 1 — single central leg
Deck height Variable — 6m on flat terrain; 20–70m on ridge country; 70–150m+ at valley crossings
Span 25m — same as Pylon B
Pylon family Same tapered segment family as Pylon B — P1 column segments stack to any height required
Corridor width ~10m — maglev guideway only (narrower than MMC-VB)
Maglev tracks 2 — northbound + southbound on single deck
Speed 600km/h — flat level deck maintained at constant elevation datum across terrain
Tubular Single 20" L80 13Cr — one per pylon (vs 2 per pylon for Pylon B)

4.2 Pylon C — Variable Height Capability

The defining feature of Pylon C for Phase 0.2 is variable height. The ridge-riding route between Newcastle and Sydney has terrain ranging from flat Hunter Valley plains to high ridge crossings at 286m elevation (Google Maps verified). The same P1 column segment — 3m long, tapered, produced by the Megafactory in 33 die profiles — stacks to whatever height the terrain requires.

Terrain type Height above ground P1 segments required Total column concrete Notes
Flat plains — Hunter Valley 6m 2 segments ~43t Minimum height — over roads, farmland, waterways
Gentle rise — foothills 12m 4 segments ~87t Standard rural crossing
Ridge section 20m ~7 segments ~152t Viaduct rides the ridgeline
Valley crossing — moderate 40m ~13 segments ~282t Arch option applicable here
Valley crossing — deep 70m ~23 segments ~499t Full arch geometry optimal
Max design height (Phase 0.2) 100m+ ~33+ segments ~717t+ Same production segment — no special tooling
The variable height capability is not a special feature — it is a consequence of the modular segment architecture. The Megafactory produces the same 3m tapered segment regardless of how many are stacked. A 6m pylon uses 2. A 70m pylon uses 23. The construction crane height changes; the module does not. This is what allows Phase 0.2 to cross the Watagan ranges at whatever elevation the deck datum requires — without tunnels, without special engineering, without bespoke fabrication.

4.3 Pylon C Structure

Component Qty/pylon Dimensions Weight (standard 6m) Notes
P1 column segment 2 (standard 6m) 4.0m OD base → 3.0m OD top, 3.0m high ~21.7t each = ~43t Same segment as Pylon B P1/P2. Stacks to 100m+. Variable quantity per height requirement.
HB1 cap beam (single-leg) 1 per pylon ~10m wide × 1.0m deep × 0.8m thick ~17t Narrower than Pylon B HB1 (17m) — single-leg corridor is ~10m wide. Maglev guideway seats cast in.
HB2 maglev girder 3 per span 25.0m span, Super-T profile, 0.40m² cross-section, 10.0m³ concrete ~24t each = ~72t total (incl rebar/PT) 3 girders not 5 — narrower single-deck corridor. Maglev guideway seats cast in via rib. 1.01t/m — single crane lift. Hub or Spoke.
STRUCTURE TOTAL (standard 6m) ~132t Columns + cap beam + girders — excluding foundation

4.4 Pylon C Weight Summary

Configuration Foundation Structure (concrete) Total concrete Notes
Standard — 6m above ground ~215t ~132t ~347t Flat terrain — Hunter Valley, urban sections
Medium — 20m above ground (~7 segs) ~215t ~236t ~451t Ridge sections — typical Watagan crossing
High — 40m above ground (~13 segs) ~215t ~380t ~595t Moderate valley crossing — arch option applies
Deep — 70m above ground (~23 segs) ~215t ~600t ~815t Deep valley — full arch geometry optimal
PYLON B for comparison ~429t ~436t ~865t MMC-VB standard — Phase 0

Pylon C at standard height (347t) is approximately 40% of the concrete mass of Pylon B (865t). At deep valley crossings (815t) the Pylon C approaches Pylon B weight — but these are exceptional spans. The Phase 0.2 route has median terrain elevation of 62m above sea level, meaning most pylons ride the ridgeline at modest height above the ridge surface (6–20m), keeping the average pylon weight well below Pylon B.

4.5 Pylon C Module Count — Phase 0.2

Module Qty/pylon (std) Phase 0.2 total (5,328 pylons) Hub or Spoke
Cutter head (hybrid) 1 5,328 Hub ONLY
Caisson ring segment (variable depth) ~10 (planning) ~53,280 Hub or Spoke — ideal Spoke candidate
Caisson head (donut, 4m OD, 0.3m) 1 5,328 Hub or Spoke — ~8.5t. Lid on caisson, pylon bears on top.
P1 column segment (3m, variable qty) 2–33 (height-dependent) ~21,312 planning Hub or Spoke
HB1 cap beam (~10m, single-leg) 1 5,328 Hub or Spoke
HB2 maglev girder (25m, 3/span) 3 15,984 Hub or Spoke — ~24t, 1.01t/m, single crane lift
Pylon head / cap 1 5,328 Hub or Spoke — ~1.9t. Top of P1 stack. Tubular tensioned here.
XA-C viaduct arm (optional) 2 (1 per side) ~10,656 Hub or Spoke — Phase 0.2 is passenger only. HVDC arms not required unless corridor upgraded. No saddle segment — bolts to outer face of standard column.
TOTAL (planning assumption) ~20 ~106,560 Hub ONLY: cutter head. All others: Hub or Spoke. Arms optional — not included in Phase 0.2 base count.
Phase 0.2 requires 106,560 modules — approximately 2% of Phase 0's 5.2 million. These are produced from a Megafactory already running at 1,473 modules per day. Phase 0.2 is an additional order of approximately 73 production days at Phase 0 run rate — before any optimisation for the simpler single-leg configuration. The production impact on the Phase 0 programme is minimal.

5. Pylon B vs Pylon C — Direct Comparison

Parameter Pylon B — MMC-VB Pylon C — MMC-VC
Programme Phase 0 — Melbourne to Brisbane Phase 0.2 — Newcastle to Sydney Direct
Legs per pylon 2 1
Deck levels 2 (freight at 6m + maglev at 17m) 1 (maglev — height varies)
Services 10+ (freight, maglev, HVDC, gas, water, fibre...) Maglev passenger only — 600km/h
Foundation 2 × 4m OD caissons — 429t 1 × 4m OD caisson — 215t (50% less)
Cap beam HB1 17m wide — 43t HB1 ~10m wide — 17t (60% less)
Longitudinal girders 5 per span (HB2 freight + HB4 maglev) 3 per span (HB2 maglev only)
Tubulars 2 × 20" L80 13Cr (one per leg) 1 × 20" L80 13Cr (one pylon)
Concrete — standard span ~865t ~347t (40% of Pylon B)
Total span weight ~1,580t (all elements) ~600t est. (all elements, standard height)
Height variability Fixed — freight 6m, maglev 17m Variable — 6m to 100m+ same production unit
Pylons in programme 96,920 (Phase 0) 5,328 (Phase 0.2)
Total modules ~5.23M ~107K (~2% of Phase 0)
Megafactory dependency Primary programme — absorbs all setup cost By-product — setup cost zero
Cost/km (volume) ~$74M/km (MMC-VB Stage 1) ~$49M/km (optimised single-leg)

6. Shared Production — One Factory, Both Pylons

The economic case for Phase 0.2 rests on the shared production argument. Every module type in Pylon C is a subset of the Pylon B module catalogue. The Megafactory does not need new tooling, new dies, new jigs, or new production lines to produce Pylon C modules. They are already in production for Phase 0.

Module type In Pylon B? In Pylon C? Same production line?
4m OD caisson ring segment Yes — 30/pylon Yes — 10/pylon (planning) Yes — identical. Best Spoke candidate — high volume, simple ring, local concrete.
Caisson head / anchor cap Yes — 2/pylon Yes — 1/pylon Yes — identical. Hub or Spoke.
Pile cap 5.5m × 5.5m Yes — 2/pylon Yes — 1/pylon Yes — identical. Hub or Spoke.
P1 column segment (3m tapered) Yes — 4/pylon Yes — 2 to 33/pylon Yes — same 33-die family. Hub or Spoke.
HB1 transverse cap beam Yes — 17m wide Yes — ~10m wide Similar — narrower die for Phase 0.2. Hub or Spoke.
HB2 longitudinal girder (25m) Yes — 5/span (~25t) Yes — 3/span (~24t) Yes — identical girder profile. Hub or Spoke. Single crane lift.
P3/P4 upper col. segment (4m) Yes — 4/pylon No — single deck N/A — not needed for Phase 0.2.
HB3 upper cap beam (17m) Yes — 1/pylon No — single deck N/A — not needed for Phase 0.2.
HB4 upper maglev girder (25m) Yes — 5/span No — HB2 used instead N/A — Phase 0.2 uses HB2 profile on single deck.
Phase 0.2 eliminates the Stage 2 upper structure entirely. The maglev runs on the single deck at whatever elevation the terrain requires — the right tool for the job. Hub or Spoke production applies to every module type except the cutter head. The cutter head is Hub ONLY — it is the most complex module in the catalogue, a hybrid steel/concrete fabrication with precision embedded cutting geometry and anchor receptacle that requires special manufacturing capability. Every other module — caisson rings, pile caps, column segments, cap beams, and girders — can be produced at a Spoke injection station using the P#7 rebar-rib option and local concrete. This is the architecture that makes the Spoke network viable: only one module type requires the Megafactory. Everything else is a local concrete pour around a Hub-supplied rib.

6.1 Production Rate Impact

Phase 0 requires 1,473 modules per day over Stage 1 (5 years). Phase 0.2 requires approximately 106,560 modules total — approximately 73 production days at Phase 0 rate. The sequencing is entirely manageable: Phase 0.2 modules are produced during Phase 0's operational ramp-up period or as an additional production run from the Line 3 girder line (which runs at 55% utilisation in Phase 0 and has headroom for Phase 0.2 orders).

Phase 0 Phase 0.2 Combined
Total modules ~5,233,680 ~106,560 ~5,340,240
Production days (at 1,473/day) ~3,553 days (~9.7 years) ~72 days ~3,625 days
Megafactory lines required 3 lines Subset of existing 3 lines 3 lines — no additional
Additional capital required ~$400-800M (Phase 0 only) Zero Zero additional

7. MMC-T Transmission — Module Lists

The MMC-TA and MMC-TB transmission tower configurations share the same foundation and pylon segment family as MMC-VB and MMC-VC. The distinctive elements are the saddle column segment (P1-S) at arm height — which has a half-circle recess on the arm-bearing face to seat the bolt-on cross-arm — and the cross-arm modules themselves (XA-A for dual-tower portal, XA-B for single-leg). All other modules are identical to the MMC-V pylon family.

7.1 MMC-TA — Dual-Tower Portal

Module Qty/pylon Hub or Spoke Notes
Cutter head (hybrid) 2 Hub ONLY 2 legs — same as MMC-VB
Caisson ring (4m OD, 1m) ~30 (15/leg × 2) Hub or Spoke Same as MMC-VB — depth geology-dependent
Caisson head (donut) 2 Hub or Spoke Same ~8.5t donut
P1 standard column segment (3m) Variable Hub or Spoke Same 33-die tapered family — stacks to required height
P1-S saddle column segment 2 (1 per leg) Hub Unique die — half-circle recess on arm-bearing face. One per leg at arm attachment height. Standard column above and below.
XA-A cross-arm (4m bolt-on, MMC-TA) 2 per arm level (1 per side) Hub or Spoke Precast concrete, ~4m long each side. Bolts into P1-S saddle socket. Conductor attachment hardware at tip. Pending detailed design.
Pylon head / cap 2 Hub or Spoke ~1.9t — top of stack — tubular tensioned here
TOTAL (planning) ~40+ Hub ONLY: cutter head. Hub: P1-S. Others: Hub or Spoke. Arms and saddle segments add ~4 modules vs standard single-level pylon

7.2 MMC-TB — Single-Leg Tower

Module Qty/pylon Hub or Spoke Notes
Cutter head (hybrid) 1 Hub ONLY Single leg
Caisson ring (4m OD, 1m) ~10 (planning) Hub or Spoke Same ring — single caisson
Caisson head (donut) 1 Hub or Spoke ~8.5t
P1 standard column segment (3m) Variable Hub or Spoke Single-leg — same tapered family
P1-S saddle column segment 1 (single leg) Hub Half-circle recess on arm-bearing face — one per arm level
XA-B cross-arm (4m bolt-on, MMC-TB) 2 (1 per side) Hub or Spoke Precast concrete, ~4m each side. Lighter than XA-A — single-leg load. Bolts into P1-S saddle. Pending detailed design.
Pylon head / cap 1 Hub or Spoke ~1.9t — top of single-leg stack
TOTAL (planning) ~18+ Hub ONLY: cutter head. Hub: P1-S. Others: Hub or Spoke. Simpler than MMC-TA — single leg, fewer foundation modules
The P1-S saddle segment is specific to MMC-TA and MMC-TB transmission towers. Viaduct configurations (MMC-VA, MMC-VB, MMC-VC) use standard circular column segments with bolt sockets cast into the column face via P#7 rib — no saddle required. The saddle geometry (half-circle recess, bolt pattern, bearing area) and arm cross-sections (XA-A, XA-B) are pending detailed design and structural FEA before final specification.

8. Longitudinal Wire Rope Continuity System

Each 25m girder span is designed as a simply-supported element for gravity loads, carried by the internal pre-tensioned strand family. A supplementary longitudinal wire rope system threads continuously through all girder spans to provide structural continuity, thermal restraint, and joint pre-compression across the full corridor length.

8.1 Concept

A continuous stainless steel wire rope runs through a smooth circular duct cast into each girder via the P#7 rib — one rope per girder, at factory-precision position. The rope threads through successive spans as the construction front advances, and is tensioned to working load before the next span is placed. Every completed span is immediately at full structural capacity. There are no weak sections at any point during construction.

Parameter Specification Notes
Rope specification 40mm 316L stainless steel, 6×36 IWRC Marine/structural grade — corrosion immune in outback environment
MBL ~1,080kN Minimum breaking load at 40mm
Working load (SF=4) ~270kN per rope 40% WLL operational tension
Ropes per span — MMC-VB 10 total (5 HB2 freight + 5 HB4 maglev) One rope per girder across both deck levels
Ropes per span — MMC-VC 3 (HB2 maglev deck) One rope per girder — single deck
Duct ID in girder ~60mm smooth bore Cast in via P#7 rib — flared entry at each end face
Structural contribution ~20% midspan moment reduction via continuity Reduces internal PT strand demand in girder section
Joint pre-compression Positive under all service loads No cracking, no water ingress at cap beam interface
Relay anchor spacing TBD — spool length determines Fixed anchor at intervals — rope terminates, new spool starts
Rope mass ~2.5 kg/m 10km spool = ~25t — spool logistics TBD by engineers

8.2 Installation Concept

10 rope spools are mounted on a rail trolley riding on the commissioned freight deck behind the construction front — one spool per girder. As each new span is placed and its duct aligned with the previous span, the rope feeds forward from the spool through the new girder duct. The spool tensioning system applies working load. The construction front advances. The rope extends span by span, always under tension, always at working load.

Step Operation
1 New girder placed on HB1/HB3 cap beam — duct aligned with previous span
2 Rope feeds forward from spool trolley through new girder duct
3 Spool tensioning system applies working load (~270kN per rope)
4 Rope locked at working load — span is immediately structural
5 Construction front advances to next span — repeat
6 At relay anchor station — rope terminates, locked permanently. New spool deploys from relay point.
The rolling spool system means every completed span is immediately at full structural capacity. No batch-and-tension delays. No weak sections during construction. The viaduct behind the construction front is always at working load — the freight rail can commission progressively as each section completes.

8.3 Engineering Design Items — Pending

The wire rope continuity concept is locked. The detailed installation methodology and spool logistics are flagged for engineering design. Key constraints to resolve:

Design item Constraint Engineering task
Spool weight 40mm SS rope at 2.5kg/m — 10km spool = 25t — impractical as single unit Determine optimum spool length vs join frequency vs trolley weight capacity
Tensioning sequence Tension/release/feed/re-tension cycle needs workable field methodology Design tensioning trolley mechanism — hydraulic, constant tension, or stepped
Relay anchor spacing Spool length determines anchor interval — 1km, 5km, 10km TBD Optimise relay station spacing vs rope join complexity vs damage isolation
Rope join detail At relay stations — join new rope to previous under controlled tension Swaged splice or mechanical coupler design — must match rope WLL
Duct alignment tolerance P#7 rib ensures factory precision — field alignment across cap beam gap Survey tolerance spec — acceptable misalignment for rope threading
Spool trolley design Rail-mounted, 10 spools, hydraulic tensioning, construction front advance Purpose-built construction equipment — Megafactory-supplied
Rope replacement De-tension section, withdraw rope, feed new rope, re-tension Maintenance procedure — relay station spacing determines replacement unit length

Longitudinal wire rope continuity system — concept locked. Installation methodology, spool logistics, tensioning sequence, and relay anchor spacing require detailed engineering design. Flagged for structural and construction engineers at detailed design stage.

9. Engineering Caveats and Next Steps

This memo is pre-feasibility grade. Numbers are within ±20–30% of detailed design values and are suitable for programme planning, cost estimation, and investment discussion. The following issues require resolution at detailed design stage before any binding structural commitments:

Issue Impact Resolution required
Foundation depth — geology Caisson ring count varies 5 to 20+ rings per leg Geotechnical investigation — bore logs along Phase 0 and Phase 0.2 alignments
Caisson diameter — 3m vs 4m Ring weight, production rate, and cost per foundation change significantly Structural analysis of load cases for single-leg Phase 0.2 — 3m may be adequate
HB1/HB3 exact sizing Cap beam weight drives Stage 1 crane requirements FEA of cap beam under freight + maglev load cases
Non-concrete split (58%) Working doc locked at ~1,580t total but concrete model gives 865t — gap needs resolving Detailed mass budget: tubulars, HVDC arms, rail, track, services, fastenings
P3/P4 column sizing Upper column load path under lateral wind + seismic needs FEA AS/NZS 1170 wind + seismic load case analysis
Maglev guideway specification Guideway mass, guideway-to-girder interface loads Engagement with maglev system supplier — depends on technology selection
Pylon C HB1 exact width ~10m assumed — depends on maglev corridor width + maintenance access Maglev system clearance requirements
Arch geometry (Phase 0.2 option) Arch die tooling, arch segment count, valley crossing span Structural arch analysis for representative ridge-valley crossings
Longitudinal wire rope — installation methodology Spool weight at practical rope lengths, tensioning sequence during construction advance, relay anchor spacing, spool trolley design Structural and construction engineering — concept locked, implementation TBD
Transverse girder connection — tongue and groove Dovetail profile on girder flanges — die variant design, engagement geometry, load transfer at joint Detail design of standard and edge girder die variants — two profiles required
Single full-width deck panel — future development Preferred long-term solution: one 25m × 17m voided slab per span replacing 5 individual girders. Eliminates all transverse connection complexity. Currently impractical due to weight and manufacturing constraints — revisit as Megafactory and viaduct crane capacity mature. Rail transport on commissioned viaduct may make this viable. Future design development — not Phase 0 scope

Pre-feasibility grade — numbers within ±20–30% of detailed design values. Detailed structural engineering by qualified engineers per AS/NZS 7000:2016, AS 3600, and AS 1170 required before any binding use. Contact brett.murrell21@gmail.com for technical enquiries.

Sovereign Build Corporation · multimodalcorridors.com · Page