MMC-VB and MMC-VC Viaduct Engineering
Pylon geometry, cap beam and girder design, HVDC arm loading, longitudinal wire-rope continuity system.
The MMC-VB and MMC-VC viaduct configurations share a common architectural pattern: dual-leg or single-leg precast concrete pylons supporting one or two decks of integrated service infrastructure across 25 m spans. This memo describes the pylon geometry, the cap beam and longitudinal girder design, the HVDC arm loading (broken-wire load case governs), and the longitudinal wire-rope continuity system that ties pylons together along the corridor. The two-stage construction methodology — Stage 1 freight viaduct commissioned first, Stage 2 upper structure built on the running freight line — is detailed for both MMC-VB (Phase 0 standard) and MMC-VC (urban passenger).
MEMO 6 — MMC-VB AND MMC-VC VIADUCT ENGINEERING — PRE-FEASIBILITY — INTERNAL WORKING DOCUMENT
SOVEREIGN BUILD CORPORATION
Memo 6 — MMC Viaduct Engineering
MMC-VB and MMC-VC Pylon Spec — Pre-Feasibility Structural Model
Dual-leg two-level viaduct for Phase 0 (Melbourne–Brisbane) and single-leg single-deck viaduct for Phase 0.2 (Newcastle–Sydney Direct). Both built from the same 4m standard foundation and the same MMC pylon segment family.
| Pylon B span wt (concrete) ~865t MMC-VB dual-leg, two-level — Phase 0 |
Pylon C span wt (standard) ~347t MMC-VC single-leg, single-deck — Phase 0.2 |
Shared foundation 4m OD Same caisson, same segments, same rig |
Shared pylon family 3m segs Same tapered column — stacks to 100m+ |
Brett Murrell — Inventor & Candidate, Robertson
May 2026 — INTERNAL WORKING DOCUMENT — PRE-FEASIBILITY GRADE
The MMC structural platform is defined by a fixed set of architectural primitives — foundation, pylon segments, cap beams, and longitudinal girders — that combine in different configurations to produce every deployment type. This memo models two specific configurations at pre-feasibility grade:
|
Pylon B — MMC-VB |
Pylon C — MMC-VC |
| Programme |
Phase 0 — Melbourne to Brisbane |
Phase 0.2 — Newcastle to Sydney Direct |
| Configuration |
Dual-leg, two-level viaduct |
Single-leg, single-deck viaduct |
| Legs per pylon |
2 (left + right) |
1 |
| Decks |
Stage 1 freight at 6m + Stage 2 maglev at 17m |
Single maglev deck — height varies with terrain |
| Services |
10+ — freight, maglev, HVDC, gas, fibre, water |
Maglev passenger only — 600km/h |
| Corridor |
2,423km inland spine |
133.2km Newcastle → Sydney direct |
| Pylons (Phase) |
96,920 pylons Phase 0 |
5,328 pylons Phase 0.2 |
| Foundation |
Standard 4m OD caisson — 2 per pylon |
Standard 4m OD caisson — 1 per pylon |
| Tubulars |
2 × 20" × 171ppf L80 13Cr (one per leg) |
1 × 13.375" × 72ppf L80 13Cr — reduced for handling at height |
| Both configurations are built from the same Newcastle Megafactory. The foundation caisson, the ring segments, the pylon column family, the cap beams, and the longitudinal girders are identical production units. The configuration is determined by how many legs are erected and how many deck levels are built — not by different module types. This is the architectural principle that makes the Megafactory economics work. |
2. Shared Foundation — The Standard 4m Caisson
Both Pylon B and Pylon C use the identical foundation system. The 4m OD caisson is the standard MMC foundation — drilled by the same rig, assembled from the same ring segment family, anchored by the same cutter head. The only difference is quantity: Pylon B requires two caissons per pylon location (one per leg); Pylon C requires one.
| FOUNDATION — STANDARD 4m CAISSON (per leg) |
| Parameter |
Specification |
Notes |
| Caisson outer diameter |
4.0m OD |
Standard MMC caisson — applies to both Pylon B and Pylon C |
| Wall thickness |
300mm |
C65 precast, P#7 skin/rib/die manufacture |
| Design depth (planning) |
15m |
Geology-dependent — range 5m to 20m+ in hard rock |
| Ring segment height |
1.0m per ring |
Design variable — 1m to 2m options; 1m is planning assumption |
| Ring segments per leg |
15 (at 1m rings, 15m depth) |
Full ring = 1 module; all identical from same production line |
| Ring segment weight |
~8.4t each |
4m OD × 300mm wall × 1m high — C65 concrete |
| Caisson head / anchor cap |
1 per leg |
~8.5t — annular donut, 4m OD × 1m ID × 0.3m high. Lid on caisson. Pylon column sits on top. Tubular passes through centre bore. |
| Cutter head (hybrid) |
1 per leg — stays in ground |
Steel/concrete hybrid — drilling tool + permanent PT anchor |
| Tubular — Pylon B (Phase 0) |
20" × 171 ppf L80 13Cr API 5CT |
One per leg — 2 per pylon. Heavy-load dual-leg platform justifies this size. Phase 0 procurement at scale. |
| Tubular — Pylon C (Phase 0.2) |
13.375" × 72 ppf L80 13Cr API 5CT |
One per pylon. Structurally adequate at all Phase 0.2 heights (7.0 MN joint capacity vs near-zero demand). Reduces joint weight from 2.35t to 1.26t — significantly better handling on narrow single-leg platform at height. |
| Joint capacity |
16.4 MN at premium connection |
95% body yield — pre-feasibility grade |
| Foundation weight per leg |
~135t (concrete) |
15 rings × 8.4t + 8.5t caisson head = ~135t (no pile cap) |
| Foundation — Pylon B (2 legs) |
~270t |
Two caissons per pylon location |
| Foundation — Pylon C (1 leg) |
~135t |
One caisson per pylon location |
Tubular sizing note: Pylon B uses 20" × 171ppf L80 13Cr (2.35t per 12m joint) — load demands and dual-leg platform justify this size. Pylon C (Phase 0.2) uses 13.375" × 72ppf L80 13Cr (1.26t per 12m joint) — structurally adequate at all Phase 0.2 heights (7.0 MN joint capacity vs near-zero tension demand) and significantly better handling on a narrow single-leg elevated work platform. The handling argument is decisive for Phase 0.2: installing 2.35t joints on a single-leg platform at 30-70m is a major rigging operation; 1.26t joints are manageable with standard pipe-handling equipment. Both grades are L80 13Cr API 5CT — same material specification, different wall thickness.
| Tubular path — Pylon B: Cutter head (foundation depth) → Caisson rings → Caisson head → P1/P2 lower columns → HB1 cap beam → P3/P4 upper columns → HB3 cap beam → Pylon head (tensioned here). The tubular runs the full height of the structure in a single continuous element — one anchor at the bottom, one tension point at the top. HB1 has upper column connection plates cast in via the rib, allowing P3/P4 to bolt on top. Pylon C omits P3/P4, HB3, HB4 — tubular runs from cutter head directly to pylon head at top of P1 stack. |
Foundation depth is the single largest design variable. Geology along the Phase 0 inland corridor is predominantly alluvial and sedimentary — likely 5–10m adequate at most locations. Hard rock sections and river crossings may require 15–20m+. The ring segment count scales directly with depth: each additional metre of depth = one additional ring segment per leg. The Megafactory produces rings at the same rate regardless of depth specification.
3. Pylon B — MMC-VB Dual-Leg Two-Level Viaduct
Pylon B is the Phase 0 standard — the dual-leg two-level viaduct that carries ten integrated services along the Melbourne to Brisbane inland spine. Two parallel pylon legs, spaced 8m centre-to-centre (inside), with a 17m total corridor width. Stage 1 builds the freight deck at 6m; Stage 2 adds the maglev deck at 17m above ground.
MMC-VB dual-leg two-level viaduct — Phase 0 standard configuration. Two legs, two decks, gold HVDC arm brackets. SketchUp pre-feasibility model — not to final engineering specification.
3.1 Pylon B Geometry
| Parameter |
Specification |
| Legs per pylon |
2 — left leg and right leg |
| Leg spacing |
8.0m centre-to-centre (inside); 17m total corridor width including overhang |
| Stage 1 freight deck height |
6.0m above finished ground level |
| Stage 2 maglev deck height |
17.0m above finished ground level |
| Span |
25m — standard across all MMC configurations |
| Pylon family |
Tapered precast concrete — same segment family as Pylon C |
| Corridor width |
~17m — freight + maglev + HVDC arms + services |
| HVDC arm bracket positions |
Cast into HB1 and HB3 cap beams via rib |
3.2 Stage 1 — Freight Viaduct (Deck at 6m)
| Component |
Qty/pylon |
Dimensions |
Weight |
Notes |
| P1/P2 lower col. segment |
4 (2/leg × 2 legs) |
4.0m OD base → 3.0m OD top, 3.0m high |
~21.7t each |
Tapered family — 33 individual die profiles. Same 3m piece stacks to 100m for terrain crossings. |
| HB1 transverse cap beam |
1 per pylon |
17.0m wide × 1.2m deep × 1.0m thick |
~43t |
Spans between two legs at 6m height. HVDC arm sockets + upper column connection plates cast in via rib. |
| HB2 longitudinal girder |
5 per span |
25.0m span, Super-T profile, 0.42m² cross-section, 10.5m³ concrete |
~25t each = ~126t total (incl rebar/PT) |
Freight deck. Pandrol e-clip rail fixing inserts cast in via rib at factory precision. 1.06t/m — single crane lift at 31% of 80t rail crane capacity. Hub or Spoke. |
| STAGE 1 CONCRETE TOTAL |
— |
— |
~206t/span |
4 columns + HB1 + 5×HB2 girders |
3.3 Stage 2 — Upper Structure (Maglev Deck at 17m)
Stage 2 is built on the commissioned freight corridor — the rail crane operates on the running freight deck, lifting upper structure components from flatbed rail wagons. The freight corridor funds and supplies its own upper-level construction.
| Component |
Qty/pylon |
Dimensions |
Weight |
Notes |
| P3/P4 upper col. segment |
4 (2/leg × 2 legs) |
2.0m OD base → 1.5m OD top, 4.0m high |
~9.3t each |
Smaller upper column family. 2 segments × 2 legs = 8m total height from HB1 top to HB3 base. |
| HB3 transverse cap beam |
1 per pylon |
17.0m wide × 1.0m deep × 0.8m thick |
~29t |
Upper cap beam — same width as HB1. Sits on P3/P4 tops; carries HB4 maglev girders. |
| HB4 longitudinal girder |
5 per span |
25.0m span, Super-T profile, 0.40m² cross-section, 10.0m³ concrete |
~24t each = ~120t total (incl rebar/PT) |
Maglev deck. Precision maglev guideway seats cast in via rib. 1.01t/m — single crane lift. Hub or Spoke. |
| Pylon head / cap |
2 per pylon (top of each leg stack) |
1.5m OD × 0.5m ID × 0.5m |
~1.9t each = ~3.8t |
Top of P3/P4 stack. Tubular anchors and tensions here against cutter head at foundation depth. Tensioning hardware cast in via rib. |
| STAGE 2 + PYLON HEAD TOTAL |
— |
— |
~190t/span |
Upper columns + HB3 + 5×HB4 girders + pylon heads |
3.4 Pylon B Weight Summary
| Element |
Concrete weight |
% of concrete total |
Notes |
| Foundation — 2 legs |
~270t |
39% |
15 rings × 8.4t + 8.5t caisson head × 2 legs (no pile cap) |
| Stage 1 — freight viaduct |
~206t |
30% |
4 columns (P1/P2) + HB1 + 5×HB2 girders |
| Stage 2 — upper structure |
~190t |
28% |
4 columns (P3/P4) + HB3 + 5×HB4 + 2 pylon heads |
| CONCRETE TOTAL |
~666t/span |
100% |
All precast concrete modules combined |
| Non-concrete elements (est.) |
~914t/span |
— |
Steel tubulars ~200t, HVDC arms ~200t, rail ~100t, services ~414t |
| TOTAL SPAN WEIGHT |
~1,580t |
— |
Matches working document locked figure ✓ |
The non-concrete elements account for approximately 45% of total span weight. The two 20" L80 13Cr tubulars alone contribute ~200t (each tubular runs the full height — foundation depth + pylon height ≈ 30-35m at ~6t/m). HVDC arms, cross-bracing, rail, track, and services make up the remainder.
3.5 HVDC Transmission Loading — MMC-VB
MMC-VB carries four HVDC bipole circuits — 72GW total at ±800kV ultra-high voltage. The HVDC arms are steel fabrications with sockets cast into HB1 (and HB3 for upper circuits) via the P#7 rib at factory precision. The arm loads transfer directly into the cap beams and thence into the pylon legs via the tubular tension element. HVDC loading must be considered alongside structural dead and live loads in the HB1 cap beam and arm socket design.
| HVDC parameter |
Value |
Notes |
| System voltage |
±800kV HVDC |
Ultra-high voltage — standard for continental corridors |
| Total corridor capacity |
72GW |
4 bipole circuits per MMC-VB corridor |
| Circuits per corridor |
4 bipole (8 poles total) |
Each bipole = 2 poles (+ and -) |
| Current per pole |
~11.2 kA |
At ±800kV, 18GW per circuit |
| Conductor bundle |
6 × 630mm² ACSR per pole |
Standard UHV HVDC bundle configuration |
| Bundle mass |
~11.1 kg/m per pole |
8 poles × 11.1 kg/m = 88.8 kg/m total |
| HVDC arm length |
~4m each side of pylon centreline |
Steel fabrication — socket cast into HB1 via P#7 rib |
| Arm attachment points |
HB1 and HB3 cap beams |
HVDC arm sockets are P#7 rib cast-in items — factory precision |
| Load type |
Value |
Design case |
Impact on structure |
| Conductor dead load (8 poles) |
~2.2t |
Permanent — all spans |
Vertical load on HVDC arms → HB1 bending |
| Insulator strings (8 poles) |
~1.2t |
Permanent |
Vertical on arms |
| HVDC arm self-weight (8 poles) |
~12.8t |
Permanent |
Vertical moment at arm-to-HB1 connection |
| TOTAL HVDC dead load |
~16t per span |
Included in non-concrete 58% |
~1% of total 1,580t span weight |
| Wind on conductors (V500) |
~33.5kN lateral |
V500 = 48m/s |
Torsion in HB1 cap beam |
| Wind on HVDC arms |
~32.5kN lateral |
V500 = 48m/s |
Torsion at arm-to-HB1 connection |
| TOTAL wind lateral (HVDC) |
~66kN |
Governs HB1 torsion design |
Combined with pylon wind loading |
| Broken wire longitudinal |
~420kN per pole |
CRITICAL CASE — one pole failure |
Governs arm socket and HB1 longitudinal design |
| The broken wire longitudinal load of ~420kN per pole is the governing design case for the HVDC arm-to-HB1 connection. When a single conductor bundle fails, the unbalanced tension pulls the arm longitudinally at full bundle tension. The P#7 rib cast-in arm socket must resist this load without yielding at the concrete-to-steel interface — this is a key structural detail requiring FEA at detailed design stage. The tubular tension element (20" L80 13Cr, 13.1 MN capacity) absorbs the resulting load path into the foundation without issue — 420kN = 0.42 MN, well within capacity. |
3.6 Pylon B Module Count — Phase 0
| Module |
Qty/pylon |
Phase 0 total (96,920 pylons) |
Hub or Spoke |
| Cutter head (hybrid steel/concrete) |
2 |
193,840 |
Hub ONLY — special hybrid steel/concrete fabrication. Precision embedded cutting geometry, anchor receptacle, thrust bearing seat. Cannot be produced at a Spoke. |
| Caisson ring segment (4m OD, 1m) |
30 (15/leg × 2) |
2,907,600 |
Hub or Spoke — simplest module. High-volume hollow ring. Ideal for Spoke injection with local concrete. |
| Caisson head / anchor cap |
2 |
193,840 |
Hub or Spoke — precision pockets cast in via rib. Spoke-producible with rebar-rib option. |
| P1/P2 lower col. segment (3m) |
4 |
387,680 |
Hub or Spoke — 33-die tapered family. Hub preferred for quality; Spoke viable for standard runs. |
| HB1 transverse cap beam (17m) |
1 |
96,920 |
Hub or Spoke — HVDC arm sockets and connection plates cast in via rib. Rebar-rib option enables Spoke. |
| HB2 longitudinal girder (25m) |
5 |
484,600 |
Hub or Spoke — Pandrol fixings cast in via rib. 25t, 1.06t/m. Single crane lift. Ideal Spoke candidate. |
| P3/P4 upper col. segment (4m) |
4 |
387,680 |
Hub or Spoke — smaller upper column. Same tapered family. Spoke-producible. |
| HB3 transverse cap beam (17m) |
1 |
96,920 |
Hub or Spoke — same geometry as HB1 without HVDC sockets. Spoke-producible. |
| HB4 longitudinal girder (25m) |
5 |
484,600 |
Hub or Spoke — maglev guideway seats cast in via rib. 24t, 1.01t/m. Single crane lift. |
| Pylon head / cap |
2 (1 per leg) |
193,840 |
Hub or Spoke — ~1.9t. Top of P3/P4 stack. Tubular tensioned here. |
| XA-C viaduct arm (4m bolt-on, per side) |
2 per level × 2 levels = 4 |
387,680 |
Hub or Spoke — bolt-on to outer face of standard column segment at HB1 and HB3 levels. Bolt sockets cast into column face via P#7 rib — no saddle segment required. |
| TOTAL (incl. arm modules) |
~60 |
~5,815,360 |
Hub ONLY: cutter head only. All others: Hub or Spoke. |
4. Pylon C — MMC-VC Single-Leg Single-Deck Viaduct
Pylon C is the Phase 0.2 configuration — the simplest MMC structural form. One leg per pylon, one deck level. Same foundation caisson, same pylon segment family, same Megafactory. The single-leg configuration reduces the per-pylon concrete weight by approximately 60% compared to Pylon B at standard height, and the variable-height capability means the same pylon serves both flat plains (6m) and deep valley crossings (70m+) with the same production unit.
MMC viaduct configuration family. Pylon C (Phase 0.2) is the Single Leg Single-Deck configuration (far left) — one caisson, one column, one cap beam, three girders. Pylon B (Phase 0 MMC-VB) is the Dual Leg 2-Deck configuration (third from left) — two caissons, two column stacks, freight deck at 6m and maglev deck at 17m. HB1 cap beam shown in green; deck girders and elements in pink. All configurations share the same foundation, segment, and cap beam production catalogue.
4.1 Pylon C Geometry
| Parameter |
Specification |
| Legs per pylon |
1 — single central leg |
| Deck height |
Variable — 6m on flat terrain; 20–70m on ridge country; 70–150m+ at valley crossings |
| Span |
25m — same as Pylon B |
| Pylon family |
Same tapered segment family as Pylon B — P1 column segments stack to any height required |
| Corridor width |
~10m — maglev guideway only (narrower than MMC-VB) |
| Maglev tracks |
2 — northbound + southbound on single deck |
| Speed |
600km/h — flat level deck maintained at constant elevation datum across terrain |
| Tubular |
Single 20" L80 13Cr — one per pylon (vs 2 per pylon for Pylon B) |
4.2 Pylon C — Variable Height Capability
The defining feature of Pylon C for Phase 0.2 is variable height. The ridge-riding route between Newcastle and Sydney has terrain ranging from flat Hunter Valley plains to high ridge crossings at 286m elevation (Google Maps verified). The same P1 column segment — 3m long, tapered, produced by the Megafactory in 33 die profiles — stacks to whatever height the terrain requires.
| Terrain type |
Height above ground |
P1 segments required |
Total column concrete |
Notes |
| Flat plains — Hunter Valley |
6m |
2 segments |
~43t |
Minimum height — over roads, farmland, waterways |
| Gentle rise — foothills |
12m |
4 segments |
~87t |
Standard rural crossing |
| Ridge section |
20m |
~7 segments |
~152t |
Viaduct rides the ridgeline |
| Valley crossing — moderate |
40m |
~13 segments |
~282t |
Arch option applicable here |
| Valley crossing — deep |
70m |
~23 segments |
~499t |
Full arch geometry optimal |
| Max design height (Phase 0.2) |
100m+ |
~33+ segments |
~717t+ |
Same production segment — no special tooling |
| The variable height capability is not a special feature — it is a consequence of the modular segment architecture. The Megafactory produces the same 3m tapered segment regardless of how many are stacked. A 6m pylon uses 2. A 70m pylon uses 23. The construction crane height changes; the module does not. This is what allows Phase 0.2 to cross the Watagan ranges at whatever elevation the deck datum requires — without tunnels, without special engineering, without bespoke fabrication. |
4.3 Pylon C Structure
| Component |
Qty/pylon |
Dimensions |
Weight (standard 6m) |
Notes |
| P1 column segment |
2 (standard 6m) |
4.0m OD base → 3.0m OD top, 3.0m high |
~21.7t each = ~43t |
Same segment as Pylon B P1/P2. Stacks to 100m+. Variable quantity per height requirement. |
| HB1 cap beam (single-leg) |
1 per pylon |
~10m wide × 1.0m deep × 0.8m thick |
~17t |
Narrower than Pylon B HB1 (17m) — single-leg corridor is ~10m wide. Maglev guideway seats cast in. |
| HB2 maglev girder |
3 per span |
25.0m span, Super-T profile, 0.40m² cross-section, 10.0m³ concrete |
~24t each = ~72t total (incl rebar/PT) |
3 girders not 5 — narrower single-deck corridor. Maglev guideway seats cast in via rib. 1.01t/m — single crane lift. Hub or Spoke. |
| STRUCTURE TOTAL (standard 6m) |
— |
— |
~132t |
Columns + cap beam + girders — excluding foundation |
4.4 Pylon C Weight Summary
| Configuration |
Foundation |
Structure (concrete) |
Total concrete |
Notes |
| Standard — 6m above ground |
~215t |
~132t |
~347t |
Flat terrain — Hunter Valley, urban sections |
| Medium — 20m above ground (~7 segs) |
~215t |
~236t |
~451t |
Ridge sections — typical Watagan crossing |
| High — 40m above ground (~13 segs) |
~215t |
~380t |
~595t |
Moderate valley crossing — arch option applies |
| Deep — 70m above ground (~23 segs) |
~215t |
~600t |
~815t |
Deep valley — full arch geometry optimal |
| PYLON B for comparison |
~429t |
~436t |
~865t |
MMC-VB standard — Phase 0 |
Pylon C at standard height (347t) is approximately 40% of the concrete mass of Pylon B (865t). At deep valley crossings (815t) the Pylon C approaches Pylon B weight — but these are exceptional spans. The Phase 0.2 route has median terrain elevation of 62m above sea level, meaning most pylons ride the ridgeline at modest height above the ridge surface (6–20m), keeping the average pylon weight well below Pylon B.
4.5 Pylon C Module Count — Phase 0.2
| Module |
Qty/pylon (std) |
Phase 0.2 total (5,328 pylons) |
Hub or Spoke |
| Cutter head (hybrid) |
1 |
5,328 |
Hub ONLY |
| Caisson ring segment (variable depth) |
~10 (planning) |
~53,280 |
Hub or Spoke — ideal Spoke candidate |
| Caisson head (donut, 4m OD, 0.3m) |
1 |
5,328 |
Hub or Spoke — ~8.5t. Lid on caisson, pylon bears on top. |
| P1 column segment (3m, variable qty) |
2–33 (height-dependent) |
~21,312 planning |
Hub or Spoke |
| HB1 cap beam (~10m, single-leg) |
1 |
5,328 |
Hub or Spoke |
| HB2 maglev girder (25m, 3/span) |
3 |
15,984 |
Hub or Spoke — ~24t, 1.01t/m, single crane lift |
| Pylon head / cap |
1 |
5,328 |
Hub or Spoke — ~1.9t. Top of P1 stack. Tubular tensioned here. |
| XA-C viaduct arm (optional) |
2 (1 per side) |
~10,656 |
Hub or Spoke — Phase 0.2 is passenger only. HVDC arms not required unless corridor upgraded. No saddle segment — bolts to outer face of standard column. |
| TOTAL (planning assumption) |
~20 |
~106,560 |
Hub ONLY: cutter head. All others: Hub or Spoke. Arms optional — not included in Phase 0.2 base count. |
| Phase 0.2 requires 106,560 modules — approximately 2% of Phase 0's 5.2 million. These are produced from a Megafactory already running at 1,473 modules per day. Phase 0.2 is an additional order of approximately 73 production days at Phase 0 run rate — before any optimisation for the simpler single-leg configuration. The production impact on the Phase 0 programme is minimal. |
5. Pylon B vs Pylon C — Direct Comparison
| Parameter |
Pylon B — MMC-VB |
Pylon C — MMC-VC |
| Programme |
Phase 0 — Melbourne to Brisbane |
Phase 0.2 — Newcastle to Sydney Direct |
| Legs per pylon |
2 |
1 |
| Deck levels |
2 (freight at 6m + maglev at 17m) |
1 (maglev — height varies) |
| Services |
10+ (freight, maglev, HVDC, gas, water, fibre...) |
Maglev passenger only — 600km/h |
| Foundation |
2 × 4m OD caissons — 429t |
1 × 4m OD caisson — 215t (50% less) |
| Cap beam |
HB1 17m wide — 43t |
HB1 ~10m wide — 17t (60% less) |
| Longitudinal girders |
5 per span (HB2 freight + HB4 maglev) |
3 per span (HB2 maglev only) |
| Tubulars |
2 × 20" L80 13Cr (one per leg) |
1 × 20" L80 13Cr (one pylon) |
| Concrete — standard span |
~865t |
~347t (40% of Pylon B) |
| Total span weight |
~1,580t (all elements) |
~600t est. (all elements, standard height) |
| Height variability |
Fixed — freight 6m, maglev 17m |
Variable — 6m to 100m+ same production unit |
| Pylons in programme |
96,920 (Phase 0) |
5,328 (Phase 0.2) |
| Total modules |
~5.23M |
~107K (~2% of Phase 0) |
| Megafactory dependency |
Primary programme — absorbs all setup cost |
By-product — setup cost zero |
| Cost/km (volume) |
~$74M/km (MMC-VB Stage 1) |
~$49M/km (optimised single-leg) |
6. Shared Production — One Factory, Both Pylons
The economic case for Phase 0.2 rests on the shared production argument. Every module type in Pylon C is a subset of the Pylon B module catalogue. The Megafactory does not need new tooling, new dies, new jigs, or new production lines to produce Pylon C modules. They are already in production for Phase 0.
| Module type |
In Pylon B? |
In Pylon C? |
Same production line? |
| 4m OD caisson ring segment |
Yes — 30/pylon |
Yes — 10/pylon (planning) |
Yes — identical. Best Spoke candidate — high volume, simple ring, local concrete. |
| Caisson head / anchor cap |
Yes — 2/pylon |
Yes — 1/pylon |
Yes — identical. Hub or Spoke. |
| Pile cap 5.5m × 5.5m |
Yes — 2/pylon |
Yes — 1/pylon |
Yes — identical. Hub or Spoke. |
| P1 column segment (3m tapered) |
Yes — 4/pylon |
Yes — 2 to 33/pylon |
Yes — same 33-die family. Hub or Spoke. |
| HB1 transverse cap beam |
Yes — 17m wide |
Yes — ~10m wide |
Similar — narrower die for Phase 0.2. Hub or Spoke. |
| HB2 longitudinal girder (25m) |
Yes — 5/span (~25t) |
Yes — 3/span (~24t) |
Yes — identical girder profile. Hub or Spoke. Single crane lift. |
| P3/P4 upper col. segment (4m) |
Yes — 4/pylon |
No — single deck |
N/A — not needed for Phase 0.2. |
| HB3 upper cap beam (17m) |
Yes — 1/pylon |
No — single deck |
N/A — not needed for Phase 0.2. |
| HB4 upper maglev girder (25m) |
Yes — 5/span |
No — HB2 used instead |
N/A — Phase 0.2 uses HB2 profile on single deck. |
| Phase 0.2 eliminates the Stage 2 upper structure entirely. The maglev runs on the single deck at whatever elevation the terrain requires — the right tool for the job. Hub or Spoke production applies to every module type except the cutter head. The cutter head is Hub ONLY — it is the most complex module in the catalogue, a hybrid steel/concrete fabrication with precision embedded cutting geometry and anchor receptacle that requires special manufacturing capability. Every other module — caisson rings, pile caps, column segments, cap beams, and girders — can be produced at a Spoke injection station using the P#7 rebar-rib option and local concrete. This is the architecture that makes the Spoke network viable: only one module type requires the Megafactory. Everything else is a local concrete pour around a Hub-supplied rib. |
6.1 Production Rate Impact
Phase 0 requires 1,473 modules per day over Stage 1 (5 years). Phase 0.2 requires approximately 106,560 modules total — approximately 73 production days at Phase 0 rate. The sequencing is entirely manageable: Phase 0.2 modules are produced during Phase 0's operational ramp-up period or as an additional production run from the Line 3 girder line (which runs at 55% utilisation in Phase 0 and has headroom for Phase 0.2 orders).
|
Phase 0 |
Phase 0.2 |
Combined |
| Total modules |
~5,233,680 |
~106,560 |
~5,340,240 |
| Production days (at 1,473/day) |
~3,553 days (~9.7 years) |
~72 days |
~3,625 days |
| Megafactory lines required |
3 lines |
Subset of existing 3 lines |
3 lines — no additional |
| Additional capital required |
~$400-800M (Phase 0 only) |
Zero |
Zero additional |
7. MMC-T Transmission — Module Lists
The MMC-TA and MMC-TB transmission tower configurations share the same foundation and pylon segment family as MMC-VB and MMC-VC. The distinctive elements are the saddle column segment (P1-S) at arm height — which has a half-circle recess on the arm-bearing face to seat the bolt-on cross-arm — and the cross-arm modules themselves (XA-A for dual-tower portal, XA-B for single-leg). All other modules are identical to the MMC-V pylon family.
7.1 MMC-TA — Dual-Tower Portal
| Module |
Qty/pylon |
Hub or Spoke |
Notes |
| Cutter head (hybrid) |
2 |
Hub ONLY |
2 legs — same as MMC-VB |
| Caisson ring (4m OD, 1m) |
~30 (15/leg × 2) |
Hub or Spoke |
Same as MMC-VB — depth geology-dependent |
| Caisson head (donut) |
2 |
Hub or Spoke |
Same ~8.5t donut |
| P1 standard column segment (3m) |
Variable |
Hub or Spoke |
Same 33-die tapered family — stacks to required height |
| P1-S saddle column segment |
2 (1 per leg) |
Hub |
Unique die — half-circle recess on arm-bearing face. One per leg at arm attachment height. Standard column above and below. |
| XA-A cross-arm (4m bolt-on, MMC-TA) |
2 per arm level (1 per side) |
Hub or Spoke |
Precast concrete, ~4m long each side. Bolts into P1-S saddle socket. Conductor attachment hardware at tip. Pending detailed design. |
| Pylon head / cap |
2 |
Hub or Spoke |
~1.9t — top of stack — tubular tensioned here |
| TOTAL (planning) |
~40+ |
Hub ONLY: cutter head. Hub: P1-S. Others: Hub or Spoke. |
Arms and saddle segments add ~4 modules vs standard single-level pylon |
7.2 MMC-TB — Single-Leg Tower
| Module |
Qty/pylon |
Hub or Spoke |
Notes |
| Cutter head (hybrid) |
1 |
Hub ONLY |
Single leg |
| Caisson ring (4m OD, 1m) |
~10 (planning) |
Hub or Spoke |
Same ring — single caisson |
| Caisson head (donut) |
1 |
Hub or Spoke |
~8.5t |
| P1 standard column segment (3m) |
Variable |
Hub or Spoke |
Single-leg — same tapered family |
| P1-S saddle column segment |
1 (single leg) |
Hub |
Half-circle recess on arm-bearing face — one per arm level |
| XA-B cross-arm (4m bolt-on, MMC-TB) |
2 (1 per side) |
Hub or Spoke |
Precast concrete, ~4m each side. Lighter than XA-A — single-leg load. Bolts into P1-S saddle. Pending detailed design. |
| Pylon head / cap |
1 |
Hub or Spoke |
~1.9t — top of single-leg stack |
| TOTAL (planning) |
~18+ |
Hub ONLY: cutter head. Hub: P1-S. Others: Hub or Spoke. |
Simpler than MMC-TA — single leg, fewer foundation modules |
| The P1-S saddle segment is specific to MMC-TA and MMC-TB transmission towers. Viaduct configurations (MMC-VA, MMC-VB, MMC-VC) use standard circular column segments with bolt sockets cast into the column face via P#7 rib — no saddle required. The saddle geometry (half-circle recess, bolt pattern, bearing area) and arm cross-sections (XA-A, XA-B) are pending detailed design and structural FEA before final specification. |
8. Longitudinal Wire Rope Continuity System
Each 25m girder span is designed as a simply-supported element for gravity loads, carried by the internal pre-tensioned strand family. A supplementary longitudinal wire rope system threads continuously through all girder spans to provide structural continuity, thermal restraint, and joint pre-compression across the full corridor length.
8.1 Concept
A continuous stainless steel wire rope runs through a smooth circular duct cast into each girder via the P#7 rib — one rope per girder, at factory-precision position. The rope threads through successive spans as the construction front advances, and is tensioned to working load before the next span is placed. Every completed span is immediately at full structural capacity. There are no weak sections at any point during construction.
| Parameter |
Specification |
Notes |
| Rope specification |
40mm 316L stainless steel, 6×36 IWRC |
Marine/structural grade — corrosion immune in outback environment |
| MBL |
~1,080kN |
Minimum breaking load at 40mm |
| Working load (SF=4) |
~270kN per rope |
40% WLL operational tension |
| Ropes per span — MMC-VB |
10 total (5 HB2 freight + 5 HB4 maglev) |
One rope per girder across both deck levels |
| Ropes per span — MMC-VC |
3 (HB2 maglev deck) |
One rope per girder — single deck |
| Duct ID in girder |
~60mm smooth bore |
Cast in via P#7 rib — flared entry at each end face |
| Structural contribution |
~20% midspan moment reduction via continuity |
Reduces internal PT strand demand in girder section |
| Joint pre-compression |
Positive under all service loads |
No cracking, no water ingress at cap beam interface |
| Relay anchor spacing |
TBD — spool length determines |
Fixed anchor at intervals — rope terminates, new spool starts |
| Rope mass |
~2.5 kg/m |
10km spool = ~25t — spool logistics TBD by engineers |
8.2 Installation Concept
10 rope spools are mounted on a rail trolley riding on the commissioned freight deck behind the construction front — one spool per girder. As each new span is placed and its duct aligned with the previous span, the rope feeds forward from the spool through the new girder duct. The spool tensioning system applies working load. The construction front advances. The rope extends span by span, always under tension, always at working load.
| Step |
Operation |
| 1 |
New girder placed on HB1/HB3 cap beam — duct aligned with previous span |
| 2 |
Rope feeds forward from spool trolley through new girder duct |
| 3 |
Spool tensioning system applies working load (~270kN per rope) |
| 4 |
Rope locked at working load — span is immediately structural |
| 5 |
Construction front advances to next span — repeat |
| 6 |
At relay anchor station — rope terminates, locked permanently. New spool deploys from relay point. |
| The rolling spool system means every completed span is immediately at full structural capacity. No batch-and-tension delays. No weak sections during construction. The viaduct behind the construction front is always at working load — the freight rail can commission progressively as each section completes. |
8.3 Engineering Design Items — Pending
The wire rope continuity concept is locked. The detailed installation methodology and spool logistics are flagged for engineering design. Key constraints to resolve:
| Design item |
Constraint |
Engineering task |
| Spool weight |
40mm SS rope at 2.5kg/m — 10km spool = 25t — impractical as single unit |
Determine optimum spool length vs join frequency vs trolley weight capacity |
| Tensioning sequence |
Tension/release/feed/re-tension cycle needs workable field methodology |
Design tensioning trolley mechanism — hydraulic, constant tension, or stepped |
| Relay anchor spacing |
Spool length determines anchor interval — 1km, 5km, 10km TBD |
Optimise relay station spacing vs rope join complexity vs damage isolation |
| Rope join detail |
At relay stations — join new rope to previous under controlled tension |
Swaged splice or mechanical coupler design — must match rope WLL |
| Duct alignment tolerance |
P#7 rib ensures factory precision — field alignment across cap beam gap |
Survey tolerance spec — acceptable misalignment for rope threading |
| Spool trolley design |
Rail-mounted, 10 spools, hydraulic tensioning, construction front advance |
Purpose-built construction equipment — Megafactory-supplied |
| Rope replacement |
De-tension section, withdraw rope, feed new rope, re-tension |
Maintenance procedure — relay station spacing determines replacement unit length |
Longitudinal wire rope continuity system — concept locked. Installation methodology, spool logistics, tensioning sequence, and relay anchor spacing require detailed engineering design. Flagged for structural and construction engineers at detailed design stage.
9. Engineering Caveats and Next Steps
This memo is pre-feasibility grade. Numbers are within ±20–30% of detailed design values and are suitable for programme planning, cost estimation, and investment discussion. The following issues require resolution at detailed design stage before any binding structural commitments:
| Issue |
Impact |
Resolution required |
| Foundation depth — geology |
Caisson ring count varies 5 to 20+ rings per leg |
Geotechnical investigation — bore logs along Phase 0 and Phase 0.2 alignments |
| Caisson diameter — 3m vs 4m |
Ring weight, production rate, and cost per foundation change significantly |
Structural analysis of load cases for single-leg Phase 0.2 — 3m may be adequate |
| HB1/HB3 exact sizing |
Cap beam weight drives Stage 1 crane requirements |
FEA of cap beam under freight + maglev load cases |
| Non-concrete split (58%) |
Working doc locked at ~1,580t total but concrete model gives 865t — gap needs resolving |
Detailed mass budget: tubulars, HVDC arms, rail, track, services, fastenings |
| P3/P4 column sizing |
Upper column load path under lateral wind + seismic needs FEA |
AS/NZS 1170 wind + seismic load case analysis |
| Maglev guideway specification |
Guideway mass, guideway-to-girder interface loads |
Engagement with maglev system supplier — depends on technology selection |
| Pylon C HB1 exact width |
~10m assumed — depends on maglev corridor width + maintenance access |
Maglev system clearance requirements |
| Arch geometry (Phase 0.2 option) |
Arch die tooling, arch segment count, valley crossing span |
Structural arch analysis for representative ridge-valley crossings |
| Longitudinal wire rope — installation methodology |
Spool weight at practical rope lengths, tensioning sequence during construction advance, relay anchor spacing, spool trolley design |
Structural and construction engineering — concept locked, implementation TBD |
| Transverse girder connection — tongue and groove |
Dovetail profile on girder flanges — die variant design, engagement geometry, load transfer at joint |
Detail design of standard and edge girder die variants — two profiles required |
| Single full-width deck panel — future development |
Preferred long-term solution: one 25m × 17m voided slab per span replacing 5 individual girders. Eliminates all transverse connection complexity. Currently impractical due to weight and manufacturing constraints — revisit as Megafactory and viaduct crane capacity mature. Rail transport on commissioned viaduct may make this viable. |
Future design development — not Phase 0 scope |
Pre-feasibility grade — numbers within ±20–30% of detailed design values. Detailed structural engineering by qualified engineers per AS/NZS 7000:2016, AS 3600, and AS 1170 required before any binding use. Contact brett.murrell21@gmail.com for technical enquiries.
Sovereign Build Corporation · multimodalcorridors.com · Page