Pre-feasibility engineering memos on the MMC system. All 11 memos in the series are now published. Each memo is a companion to one or more patents in the MMC Patent Family, or to a specific platform component (megafactory, foundations, viaduct, transmission, station architecture). To request advance access for partner discussion, contact the team.
Memo 1 · Manufacturing
The parallel-line manufacturing principle, Hub-and-Spoke deployment, and a worked example: MMC-TB single-leg transmission tower over 500 km. 110,000 modules, 11 designs, dedicated steel fabrication line for cutter heads. Companion to Patent 7.
Memo 2 · Transmission
Worked tension calculations for the MMC transmission tower family — 132 kV through ±1100 kV UHVDC. Three deployment options on a single SKU. Companion to Patents 5 and 6.
Memo 3 · Foundations
The Anchor Tension System (ATS) caisson — drilled and grouted foundations across the MMC platform. Single integrated drilling-and-installation pass. Companion to Patents 1, 2, 3, 4.
Memo 4 · Phase 0
Direct technical comparison: SBC Phase 0 multimodal viaduct vs the High Speed Rail Authority's tunnel-based passenger rail. Cost, schedule, capability, deliverability.
Memo 5 · Phase 0-2
The single-leg single-deck MMC-VC viaduct deployed for Phase 0-2 — ridge route through the Watagans. Engineering case for a 15-minute Newcastle-to-Sydney maglev journey.
Memo 6 · Viaduct Engineering
Pylon geometry, cap beam and girder design, HVDC arm loading, longitudinal wire-rope continuity system. Module catalogues. Companion to Patents 4 and 5.
Memo 7 · MMC-VA
The continental rollout configuration — five integrated service levels (freight, aqueduct, services, hyperloop reservation, maglev) on a dual-leg viaduct at 50m to top deck.
Memo 9 · Passenger Technology
An apples-to-apples comparison of maglev vs high-speed rail, both deployed on the MMC viaduct platform — and why the continental Australian case is decisively maglev geography.
Memo 10 · Transmission
UHVDC trunk for bulk transfer. VSC HVDC backbone for solar collection. MVDC for towns and the multimodal viaduct. Three voltage levels in parallel — uses only commercially proven technology, with upgrade paths as DC-DC converter research matures.
Memo 11 · Stations & Ramps
The unifying principle: stopping trains use side tracks; main alignments run corridor speed uninterrupted. Applied at two scales — freight ramps to ground-level terminals + maglev side guideways on the 4-track-capable upper deck. Built on the two-legged MMC pylon (embodiment of the company logo) at 25 m spacing. Worked example: Newcastle–Sydney 27 min with 2 stops (80% faster than current). Daily capacity ~100-145 movements/direction/day. Switch speed identified as the engineering scaling variable for corridor experts.
Memo 12 · Platform
The bearing-only interface between the sacrificial cutter head and the lead caisson ring. Sets out AS 3600 bearing capacity (FS 2.9), the hybrid hard-faced thrust pad system with debris sleeve, and the dual-purpose Anchor receptacle. Bidirectional WOB control via drill pipe lift.
Memo 13 · Platform
The castellated dog-clutch joints between adjacent caisson rings. Skin-friction-breaking torque transmission, with four engineering mitigations for concrete-on-concrete cyclic shear: radiused roots, elastomeric shims, zero-draft faces, closed-loop confinement.
Memo 14 · Platform
The economic case for the disposable cutter head. ~$3K MMC Hub production vs ~$10K bespoke (75-85% saving). Single standardised design across the corridor with geological adaptation via insert replacement rates. Net Phase 0 saving ~$2.6-7.4B from single-pass methodology.
Memo 15 · Platform
The Hub-and-Spoke production architecture for ~2.1 million precast caisson rings across the Phase 0 corridor. Two ring variants (standard and lead), ~$390 mid-range unit cost, ~$1 billion aggregate Phase 0 caisson ring programme. Companion to Patents 1 and 7.