The MM Lines laid together on the seabed in one armoured bundle, joined to the land at each landfall, and built in stages.
The land corridor carries the MM Lines on a structure. At sea there is no structure: the lines are laid on the seabed, bundled and armoured, and come ashore at a near-shore manifold. Where passengers and freight must cross, a tunnel is added on the same lane (see Models).
Status: draft. Demonstrative, not detailed design. Sizes and layouts are indicative.
A subsea line lane carries the MM Lines across the sea without a tunnel. The lines are laid on the seabed, not in a structure. Each item below is an MMC proposal; the published practice it builds on is cited.
| MMC proposal | Published practice it builds on |
|---|---|
| Bundle-deployed lines. The lines for a lane are packed together and laid as one bundle. Bundling adds strength. | Oilfield pipeline bundles place pipelines plus power, signal and fibre lines inside one steel carrier pipe, tested before launch and towed out. The longest single bundle is 7.7 km; four bundles in the Andrew field total 27.8 km[A][D]. |
| Armoured construction and damage prevention. Armour, burial and protection zones on every lane. | Most cable faults are accidental: about 150–200 a year worldwide, 70–80% from fishing and anchors[E]. Armouring is standard; Marinus Link Stage 1 uses single-wire armoured cable[F]. |
| Service and repair vessels, spares on hand. Vessels built for repair, based along the lanes, carrying spare cable and parts. | Fewer than 70 cable repair ships work worldwide; long lead times for spares extend outages[G]. |
| Bespoke lay vessels. Vessels designed to lay the bundles. | Cable makers run their own lay vessels; Prysmian laid North Sea Link with its vessel Giulio Verne[H]. |
| Manufacture in hubs, close to the lanes. Cable for each line made locally — Australia as the example. | All advanced HVDC subsea cable factories are in the Northern Hemisphere. SunCable has proposed a factory at Bell Bay, Tasmania, making 1,200–1,600 km a year[I][J]. |
| Land-to-sea links and tie-in points. Landfall stations join the lane to the land corridor; seabed tie-ins let lines branch or join. | Subsea oilfield practice: manifolds, pipeline end terminations (PLET/PLEM) and jumpers connect lines on the seabed; umbilicals carry power, hydraulics and fibre[K][L]. |
Distance and depth reached to date: Viking Link (UK–Denmark) runs 765 km at ±525 kV, 1.4 GW[M]; Tyrrhenian Link cable is laid to 2,150 m[C]; the Crete–Cyprus link is designed for 3,000 m[N]. The Australian links are longer (1,800–9,900 km); the proposed AAPowerLink needs two 4,300 km cables[I].
MMC-DWG-007-01 shows the idea, not detailed design: a bundle cross-section, the lane in the seabed, the shore tie-in, and installation by tow. Sizes are indicative.
A second way to lay a lane, beside the towed bundle in 007-01. Each line has its own vessel: one for the HVDC cable, one for the water pipe, one for the fibre cable. The centre vessel carries the pipe and pulls all three lines together, adds the armour, and lays them as one bundle over the stern. The lay method varies by lane.
Published vessels: the largest cable-lay ships carry 10,000 t and 7,000 t carousels and hold station on DP3 (Prysmian). Reel-lay vessels lay steel pipe up to 20 in from a 5,600 t reel, and lay cable strapped to the pipe in one pass (Subsea7, Seven Vega). Armouring at sea is not current practice; armour is applied in the factory today. The armouring station on the centre vessel is an MMC proposal.
Two arrangements are drawn. 007-02: open sea, the three vessels on dynamic positioning with a gap between hulls (~30–60 m, assumed) and the lines crossing on chutes under tension. 007-03: sheltered water, the three vessels tied alongside with fenders between the hulls.
At each landfall the bundle ends at a near-shore manifold, where new lanes are connected subsea and lines go to land as needed: see Subsea Equipment.
A lane can be built in stages. Option one: lay the bundle first, so power, fibre and pipelines flow early, then build the tunnel on the same lane later for passengers and freight. Option two: bundle only, where a tunnel is too deep or too long. Option three: tunnel only, carrying all lines inside it.