Build · Pipelines

Pipeline installation.

The pipelines go in at deck level on the MMC-VD services deck, 19 m up. Large lines are welded into strings at a launch station; drive rollers along the deck move them, with a push unit at the start: push and drive. Smaller lines come on spools, fed from a lay train on the service rail — the same idea as the subsea lay.

Into the deck, not up from the ground.

Nothing is lifted pipe by pipe from the ground. Everything reaches the services deck by the service rail, and every line rides the same rollers along the deck. The rollers drive the pipe: drive roller units at intervals grip it and move it along, and a push unit at the launch station starts each string and adds thrust. The rollers stay in place for inspection and repair.

Status: draft. Demonstrative, not detailed design. Joint length, roller spacing, drive positions and station layout are indicative.

MMC-DWG-003-16 Pipeline installation on the services deck, demonstrative drawing
MMC-DWG-003-16 · Pipeline Install, Services Deck — demonstrative, not detailed design. Select to enlarge.

Large lines — welded strings from a launch station

Water, gas, liquid fuels and hydrogen run at 0.6–1.0 m on MMC-VD: too large to reel. They go in as welded strings.

  1. Pipe joints, about 12 m each, come up to the launch station by the service rail. The launch station is a deck-level platform on its own frame at the end of a section.
  2. Each joint is welded to the end of the string in the welding booth.
  3. The weld is tested and the joint coated.
  4. The push unit starts the string onto the deck rollers.
  5. Drive roller units along the deck move the string forward by one joint length, the push unit adding thrust; the next joint is welded on, and the cycle repeats.
  6. At the far end the string is tied in, and the line is pressure-tested end to end.

Push and drive — the rollers move the pipe

The rollers do not only carry the pipe; they move it. A drive roller unit is a motorised roller under the pipe with a pinch roller above it and guide rollers at the sides (view E). Units are spaced along the deck. Each one moves only its own length of string, so no single machine has to push the whole line, and a long string is not pushed hard from one end.

A rough figure, for scale. Assumptions: the 1.0 m water pipe in steel with a 12.7 mm wall, empty, about 310 kg per metre; a friction coefficient of 0.1 for pipe on rollers, the figure used in pipeline design softwareD; a level deck. Then each kilometre of string needs about 31 t of force to move, and a 1% grade adds about 3 t per kilometre. With a drive unit every 100 m, each unit supplies about 3 t. Not checked: traction of each drive roller, load on each roller, and expansion of a long steel string with temperature.

Precedent: in trenchless pipe installation, the welded string is already laid out on rollers and moved along them — pulled into the bore in horizontal directional drillingD, and pushed by a pipe thruster in the Direct Pipe methodE. Driving the pipe with powered rollers along a whole route is an MMC proposal.

Smaller lines — spools on a lay train

Lines small enough to reel come on spools, like the subsea lay method. Published reel limits: steel pipe is reeled up to 20 in, about 0.5 mA; spoolable composite pipe is made up to 8 inB, on spools up to about 16 ft acrossC. On MMC-VD that is the fibre duct, and any smaller line added later.

  1. Spools are loaded onto spool wagons at the depot.
  2. The lay train runs along the service rail onto the services deck.
  3. Each line passes a straightener and a tensioner, then is fed sideways onto its rollers.
  4. As the train moves, the line is laid along the deck.
  5. At the end of a spool, the next spool is joined on and laying continues.

Line by line

LineSize on MMC-VD (002-08)Installed by
Water1.0 mWelded strings, launch station
Gas0.75 mWelded strings, launch station
Liquid fuels0.6 mWelded strings, launch station
Hydrogen0.75 mWelded strings, launch station
Fibreduct 0.5 mSpools on the lay train
Spare1.0 mEither, by the line it carries

Inspection and repair

Because every line sits on rollers, a damaged length can be cut out and replaced on the deck, or the line driven back to the launch station. The service rail brings the crew, the pipe and the spools.

The model: MMC-VD and drawing 002-08. The other way to lay pipes on the platform is hung under the freight deck, on MMC-VB.

Sources

  1. A · Subsea7, Seven Vega vessel datasheet (reel products 4–20 in)
  2. B · Materials Performance, Baker Hughes onshore composite flexible pipe, up to 8 in
  3. C · Pipeline & Gas Journal, RTP spools up to 16 ft in diameter (Mar 2026)
  4. D · Technical Toolboxes, HDD constructability: the pipe string is placed on rollers; pull-force inputs, pipe–roller friction 0.1
  5. E · Herrenknecht, Direct Pipe: pipeline laid out on rollers, pushed by the Pipe Thruster