Advantage 01

Cost per km is the winning point.

High-speed rail is built as one-off projects, and the costs blow out. MMC shares the cost of each km across standard parts and many services.

One-off projects blow out.

High-speed rail is built as one-off projects, and the costs blow out. MMC is built from standard modular components and carries many services on one structure, so the cost of each km is shared. That is the MMC proposal; the evidence below is from others.

HS2 · UK
£37.5 bn → £88–103 bn

First estimate to the May 2026 cost to complete London–Birmingham.1,2

California HSR
US$33.6 bn → US$126–231 bn

2008 Phase 1 estimate to the draft 2026 plan.5,6

EU high-speed lines
+78%

Average line-level overrun, European Court of Auditors.7

Rail projects, worldwide
+44.7%

Average cost escalation on 58 rail projects.8

From £37.5 bn to £88–103 bn.

What drove the increase

HS2 Ltd’s split of a £48.6 bn increase:4

Inflation
34%

Underestimation
32%

Inefficient delivery
23%

Scope change
11%

From US$33.6 bn to US$126–231 bn.

Phase 1 was put at US$33.6 bn in the 2008 Business Plan (2008 dollars).5 The draft 2026 plan gives US$231.3 bn on legacy assumptions, or about US$126.2 bn after scope cuts.6

Overruns are the norm.

The European Court of Auditors found an average cost overrun of 78% at line level across the high-speed lines it audited; every line audited ran more than 25% over.7

Across 258 transport projects, the 58 rail projects showed an average cost escalation of 44.7%.8

A$65 m to A$284 m per km.

Per-km figures are derived (cost ÷ length). Price bases and scope differ between projects (stations, tunnels, rolling stock), so they are not like-for-like.

Standard parts, shared structure, one method.

MMC-VB · freight stage
~A$74 m / km

MMC planning estimate, volume pricing, Phase 0.1 (111 km).12

MMC-VB · full, 10+ services
~A$146 m / km

MMC planning estimate, volume pricing, Phase 0.1 (111 km).12

Sydney–Newcastle HSR · 1 service
~A$284 m / km

Stages 1A and 1B, derived.10,11

MMC figures are pre-feasibility planning estimates from the MMC memo series, not measured costs.
MMC-DWG-002-02 MMC-VB Viaduct
MMC-DWG-002-02 · MMC-VB Viaduct. One structure: freight below, maglev above, HVDC on the arms, services in the structure. Select to enlarge.

Cost per service. Built separately, every service needs its own corridor, land, approvals and path through the city. On MMC those are paid once and shared, and the corridor carries every service across borders between nations. Many services, one corridor (estimate) →

Economics: cost and overruns →   How it is built →

References.

  1. Institute for Government, HS2: costs and controversies. www.instituteforgovernment.org.uk
  2. UK Department for Transport, HS2 reset (oral statement), 19 May 2026. www.gov.uk
  3. UK Department for Transport, Full Business Case: HS2 Phase One, 2020. assets.publishing.service.gov.uk
  4. UK National Audit Office, High Speed Two reset, June 2026. www.nao.org.uk
  5. Eno Center for Transportation, Timeline of California High-Speed Rail Cost Estimates, 2018. enotrans.org
  6. Railway Age, CHSRA Issues Draft 2026 Business Plan, 2026. www.railwayage.com
  7. European Court of Auditors, Special Report 19/2018: A European high-speed rail network: not a reality but an ineffective patchwork, 2018. op.europa.eu
  8. Flyvbjerg, Holm and Buhl, Underestimating Costs in Public Works Projects: Error or Lie?, Journal of the American Planning Association 68(3), 2002. arxiv.org
  9. Parliamentary Library, High-speed rail (FlagPost), January 2014. aph.gov.au
  10. Infrastructure Australia, High Speed Rail – Newcastle to Sydney, 2026. infrastructureaustralia.gov.au
  11. Minister for Infrastructure C. King, media conference, Newcastle, 2026. minister.infrastructure.gov.au
  12. MMC Memo 4, MMA Phase 0 Maglev vs HSRA (pre-feasibility). multimodalcorridors.com
← All advantages02 · Modular components →