Economics · Assumptions

Build cost assumptions.

What it costs to build each service separately, against one MMC corridor carrying them all: every figure, how it was worked out, and where it comes from.

How each figure is marked.

Status: Published Derived Assumed MMC estimate Rough
Published: a figure as stated by the source. Derived: calculated from published figures (the calculation is shown). Assumed: a value chosen for the estimate. MMC estimate: from MMC planning documents. Rough: a planning figure with no single published source. All figures on these pages are estimates.

Built separately, or on one corridor.

ItemValueBasisStatus
Passenger rail — high-speed rail, Sydney–Newcastle~A$284 m/km~A$55 bn ÷ 194 km (Stages 1A and 1B)1Derived
Freight rail — Inland Rail~A$28 m/km>A$45 bn ÷ ~1,600 km2Derived
Power transmission — HumeLink (overhead)~A$13 m/km~A$5 bn ÷ 365 km3Derived
Power transmission — HumeLink (underground option)up to A$11.5 bnTransgrid estimate for undergrounding3Published
Water pipeline — Fitzroy to Gladstone~A$8.5 m/km~A$1 bn ÷ 117 km (about 30 GL a year)4Derived
Gas pipeline — Northern Gas Pipeline~A$1.3 m/kmA$800 m ÷ 622 km (2015, 14-inch)5Derived
Land and offsets, each corridor~A$2.6 m/kmBiodiversity offsets ~A$2.09 m/km + landholder payments ~A$0.475 m/km, 70 m easement6Published
Five services built separately~A$335 m/kmSum of the five services above plus land and offsets for eachDerived
MMC-VB, ten or more services on one structure~A$146 m/kmMMC-VB at volume pricing7MMC estimate
How per-km figures are derived: published project cost ÷ route length. Five services built separately: 284 + 28 + 13 + 8.5 + 1.3 = ~A$335 m/km, before land and offsets for each corridor.

Where single services get expensive.

ItemValueBasisStatus
Approvals, large transmission lines3–7+ yearsConcept to construction approval8Published
Land access delay — VNI West+2 yearsLandholder engagement on access and easements9Published
Cost of transmission delayA$40 bn per yearNational Electricity Market, each year of delay (Clean Energy Investor Group)10Published
Reaching the city — Sydney desalination pipeline19 shafts7.5 km under Botany Bay and 6.4 km micro-tunnelling over 17 km11Published

MMC-VB costed from its parts list: the workings →

What the comparison takes as given.

References.

  1. Infrastructure Australia, High Speed Rail – Newcastle to Sydney, 2026. infrastructureaustralia.gov.au
  2. Minister for Infrastructure C. King, record investment in the freight rail network and consolidating Inland Rail, May 2026; ACIL Allen, Inland Rail verification summary, 20 November 2025. minister.infrastructure.gov.au
  3. RenewEconomy, Is HumeLink worthwhile?; HumeLink gets federal green tick. reneweconomy.com.au
  4. Infrastructure Magazine, Fitzroy to Gladstone Pipeline; Queensland Government. infrastructuremagazine.com.au
  5. Engineering News, Jemena selected to build A$800m NT gas pipeline, 17 November 2015. engineeringnews.co.za
  6. Energy Magazine, Report highlights costs for undergrounding electricity infrastructure. energymagazine.com.au
  7. MMC Memo 4, MMA Phase 0 Maglev vs HSRA (MMC-VB, volume pricing). multimodalcorridors.com
  8. Chambers and Partners, Power Generation, Transmission and Distribution 2026 — Australia. chambers.com
  9. ESD News, Landholder negotiations delay VNI West by two years. esdnews.com.au
  10. Energy Magazine, Is the grid becoming the energy transition's biggest bottleneck? energymagazine.com.au
  11. McConnell Dowell, Sydney Desalination Plant — Water Delivery Alliance. mcconnelldowell.com

Back to the Economics section →