Economics · Assumptions

Parts-list costing: MMC-VB.

MMC-VB costed from its own parts list: each part per km, the rate applied, and what it comes to, at current market rates.

How each figure is marked.

Status: Published Derived Assumed MMC estimate Rough
Published: a figure as stated by the source. Derived: calculated from published figures (the calculation is shown). Assumed: a value chosen for the estimate. MMC estimate: from MMC planning documents. Rough: a planning figure with no single published source. All figures on these pages are estimates.

Foundations, pylons and beams.

PartQuantity per kmRate and costStatus
Precast concrete: pylon joints, caisson rings and heads, cross beams, longitudinal beams~21,700 m³~54,230 t per km ÷ 2.5 t/m³; rate A$2,000–3,500 per m³ supplied and erected → A$43–76 m1Assumed
Tension tubulars (oilfield casing)~690 tUS$3,031 per t (US OCTG, September 2026) ÷ 0.687 = ~A$4,410 per t → ~A$3 m1,2Published
Foundation drilling and caisson install80 caissons at 15 mA$100,000–250,000 per caisson → A$8–20 m1Assumed
Parts with no mass set: cutter heads, anchor latches, tension locks, HVDC arm modules80–240 of eachAllowance → A$2–5 m1Assumed
StructureA$56–104 m per kmDerived

The freight viaduct.

PartQuantity per kmRate and costStatus
Freight track, 3 tracks3 track-kmA$2–3 m per track-km → A$6–9 m1Assumed
Overhead line3 km of contact wire, 20 portalsA$1–2 m per km → A$3–6 m1Assumed
Stage 1: structure + freightA$65–119 m per km (midpoint ~A$92 m)Derived

All services on the structure.

PartQuantity per kmRate and costStatus
Maglev guideways, 22 guideway-km, 80 segmentsA$15–30 m per guideway-km on the shared structure → A$30–60 m1Assumed
Gas pipe 750 mm X80, water pipe 1 m, hydrogen pipe3 km of pipeA$1.5–4 m per km each, supplied, welded and hung → A$5–11 m1Assumed
HVDC conductors and insulators; fibre 96-duct bank6 conductor-km, 240 insulator strings; 96 duct-kmAllowance → A$2–6 m1Assumed
Full MMC-VBA$102–196 m per km (midpoint ~A$149 m)Derived
Result: Stage 1 A$65–119 m per km; full MMC-VB A$102–196 m per km, at current market rates. At the midpoints, the structure (~A$80 m) is about 54% of the full cost (~A$149 m).

Built elevated lines.

ItemValueBasisStatus
Sydney Metro Skytrain viaduct~A$85 m/kmA$340 m contract (2013) for ~4 km of single-deck, two-track viaduct3Derived
Shanghai maglev~US$40 m/kmUS$1.2 bn for ~30 km: line, vehicles, maintenance facility and stations (2004)4Published

Memo figures beside the parts range.

ItemValueBasisStatus
Stage 1, freight viaduct (volume pricing)A$74 m/kmParts range A$65–119 m; memo at the low end5MMC estimate
Full MMC-VB (volume pricing)A$146 m/kmParts range A$102–196 m; memo near the midpoint5MMC estimate
Current rates, pre-volumeA$235 m/kmAbove the top of the parts range (A$196 m)5MMC estimate
Megafactory long-term target~A$25 m/kmWright's Law target; not tested by the parts costing5MMC estimate
The memos have not been updated. Their figures are shown as published.

What the costing takes as given.

References.

  1. MMC, MMC-VB modular components: parts list per pylon and per km. multimodalcorridors.com
  2. GMK Center, Average prices for OCTG pipes in the US rose by 17% y/y in September, 12 October 2026 (US$3,031 per tonne). gmk.center
  3. Railway Technology, Sydney Metro Northwest skytrain (A$340 m contract, 2013). railway-technology.com
  4. NextBigFuture, Shanghai maglev cost (9.93 bn yuan, US$1.2 bn for 30 km, ~US$40 m per km). nextbigfuture.com
  5. MMC Memo 4, MMA Phase 0 Maglev vs HSRA (cost figures, May 2026). multimodalcorridors.com

Back to the Economics section →