MMC-VB costed from its own parts list: each part per km, the rate applied, and what it comes to, at current market rates.
| Part | Quantity per km | Rate and cost | Status |
|---|---|---|---|
| Precast concrete: pylon joints, caisson rings and heads, cross beams, longitudinal beams | ~21,700 m³ | ~54,230 t per km ÷ 2.5 t/m³; rate A$2,000–3,500 per m³ supplied and erected → A$43–76 m1 | Assumed |
| Tension tubulars (oilfield casing) | ~690 t | US$3,031 per t (US OCTG, September 2026) ÷ 0.687 = ~A$4,410 per t → ~A$3 m1,2 | Published |
| Foundation drilling and caisson install | 80 caissons at 15 m | A$100,000–250,000 per caisson → A$8–20 m1 | Assumed |
| Parts with no mass set: cutter heads, anchor latches, tension locks, HVDC arm modules | 80–240 of each | Allowance → A$2–5 m1 | Assumed |
| Structure | A$56–104 m per km | Derived |
| Part | Quantity per km | Rate and cost | Status |
|---|---|---|---|
| Maglev guideways, 2 | 2 guideway-km, 80 segments | A$15–30 m per guideway-km on the shared structure → A$30–60 m1 | Assumed |
| Gas pipe 750 mm X80, water pipe 1 m, hydrogen pipe | 3 km of pipe | A$1.5–4 m per km each, supplied, welded and hung → A$5–11 m1 | Assumed |
| HVDC conductors and insulators; fibre 96-duct bank | 6 conductor-km, 240 insulator strings; 96 duct-km | Allowance → A$2–6 m1 | Assumed |
| Full MMC-VB | A$102–196 m per km (midpoint ~A$149 m) | Derived |
| Item | Value | Basis | Status |
|---|---|---|---|
| Stage 1, freight viaduct (volume pricing) | A$74 m/km | Parts range A$65–119 m; memo at the low end5 | MMC estimate |
| Full MMC-VB (volume pricing) | A$146 m/km | Parts range A$102–196 m; memo near the midpoint5 | MMC estimate |
| Current rates, pre-volume | A$235 m/km | Above the top of the parts range (A$196 m)5 | MMC estimate |
| Megafactory long-term target | ~A$25 m/km | Wright's Law target; not tested by the parts costing5 | MMC estimate |