What each service on the corridor is charged for use, the volume assumed, and how the income per km is worked out.
| Item | Value | Basis | Status |
|---|---|---|---|
| Freight — charge method | Per train-km | A set minimum charge per train per km to cover cost; pricing by weight and volume per km to follow | Assumed |
| Freight — rate | ~A$15 per train-km | European full-cost benchmark €9.39 per train-km (18 countries) × A$1.62 per €1,4 | Derived |
| Freight — volume | 20 trains a day | Trunk corridor, each direction combined | Assumed |
| Freight — income | ~A$0.11 m per km a year | 20 × 365 × A$15 | Derived |
| Gas — rate | ~A$1.44 per GJ | APA, Moomba–Wilton reference tariff5 | Published |
| Gas — rate per km | ~A$0.0011 per GJ-km | A$1.4357 ÷ ~1,300 km5 | Derived |
| Gas — volume | 100 PJ a year | Trunk pipeline throughput | Assumed |
| Gas — income | ~A$0.11 m per km a year | 100,000,000 GJ × A$0.0011 | Derived |
| HVDC — rate | ~A$10 per MWh per 1,000 km | Planning figure | Rough |
| HVDC — volume | 12.3 TWh a year | 2 GW line at 70% use | Assumed |
| HVDC — income | ~A$0.12 m per km a year | 12.3 m MWh × A$0.01 | Derived |
| Fibre — rate | ~A$2,500 per duct-km a year | Planning figure | Rough |
| Fibre — volume | 20 ducts leased | Of the ducts on the structure | Assumed |
| Fibre — income | ~A$0.05 m per km a year | 20 × A$2,500 | Derived |
| Water — rate | ~A$500 per ML per 1,000 km | Planning figure | Rough |
| Water — volume | 75 GL a year | MMC-VB water capacity6 | MMC estimate |
| Water — income | ~A$0.04 m per km a year | 75,000 ML × A$0.50 | Derived |
| Five services — total | ~A$0.43 m per km a year | Sum of the five | Derived |
| Shared running cost | ~A$0.25 m per km a year | Rail fixed upkeep A$124,000 per track-km (2020 dollars) × 2 tracks7 | Derived |
| Left after running cost | ~A$0.18 m per km a year | 0.43 − 0.25 | Derived |
| Item | Value | Basis | Status |
|---|---|---|---|
| Australia — ARTC | Weight per km + flagfall per train-km | A$9.033 per 1,000 gross tonne-km + A$3.613 per km (SSFL, 2023); about A$30 per train-km for a 3,000-tonne train1 | Derived |
| Europe — average 2024 | Per train-km | €2.96 per freight train-km (about A$4.80): direct cost of running the train plus mark-ups where the market can bear them2,3 | Published |
| Europe — full-cost benchmark | Per train-km | €9.39 per train-km, weighted average of 18 countries (about A$15)4 | Published |
| Europe — Belgium 2023 | Per train-km | €2.28 gross; €1.69 after subsidy8 | Published |
| United States — Class I | Not charged separately | Track and trains owned together; full freight rate 4.4 US cents per ton-mile (2020)9 | Published |
| MMC | Per train-km, then weight and volume | Minimum charge per train-km to cover cost; then the larger of weight (tonnes) or volume (m³) per km | Assumed |
| Item | Value | Basis | Status |
|---|---|---|---|
| Stage | Final stage | Once the corridors, power towns and PV farms are built and running; additional to the totals above | Assumed |
| Town spacing | 100 km | Towns along the corridor | Assumed |
| Data centre at each town | 100 MW | Powered from the PV farms at the towns | Assumed |
| Market rate | US$196.25 per kW a month | Average power asking rate, year-end 202510 | Published |
| Revenue per data centre | ~A$343 m a year | 100,000 kW × US$196.25 × 12 ÷ 0.687 | Derived |
| Corridor share | ~10% | Of data centre revenue | Assumed |
| Corridor income per town | ~A$34 m a year | 10% × A$343 m | Derived |
| Corridor income per km | ~A$0.34 m a year | A$34 m ÷ 100 km | Derived |
| Item | Value | Basis | Status |
|---|---|---|---|
| Standard fibre, round trip | ~10 ms per 1,000 km | Light in glass at just under 200,000 km a second11 | Derived |
| Hollow-core fibre, round trip | ~7 ms per 1,000 km | About 33% lower latency than standard fibre12 | Derived |
| Starlink, median | ~37–45 ms | Measured, US, 202513 | Published |
| Geostationary satellite, median | >670 ms | Measured, US, Q1 202614 | Published |