The MMA plan for Australia, worked as an example of the MMC vision: 150 towns on seven corridors, the solar power they supply, the flood water harvested, the water stored, and the pumped hydro battery. Working figures; every assumption is listed in section 08.
The seven MMA corridors, including corridor 7 from Perth to Port Hedland, plus the spine and spurs.
One every 100 km along the seven corridors, as drawn on MMC-DWG-009-04.
Where the corridors cross, including the Alice Hub, Mount Isa and Kalgoorlie.
Each town is the centre of its own solar and farmland, built ring by ring.
| Hub size | Outer radius | Solar area a town | 150 towns | Energy a year at 24% |
|---|---|---|---|---|
| Australian hub, 6.7 GW | 9.4 km | 267 km² | 1,000 GW | 2,102 TWh |
| 10.0 GW | 11.5 km | 400 km² | 1,500 GW | 3,154 TWh |
| 15.0 GW | 14.0 km | 600 km² | 2,250 GW | 4,730 TWh |
| 20.0 GW | 16.1 km | 800 km² | 3,000 GW | 6,307 TWh |
| Quantity | Figure | How it is calculated |
|---|---|---|
| Capacity of one town | 6.7 GW | 1,000 GW ÷ 150 towns |
| Solar area of one town | 267 km² | 6.7 GW × 40 km² per GW |
| Energy from one town | 14,016 GWh a year | 6.7 GW × 8,760 hours × 24% |
| Capacity of 150 towns | 1,000 GW | 150 × 6.7 GW |
| Solar area of 150 towns | 40,000 km² | 1,000 GW × 40 km² per GW |
| Energy from 150 towns | 2,102 TWh a year | 1,000 GW × 8,760 hours × 24%; 1,927 TWh at 22%, 2,278 TWh at 26% |
Equal to the output of about 4 towns.
| Quantity | Figure | How it is calculated |
|---|---|---|
| Energy to lift 1 GL by 550 m | 1.50 GWh | 1,000 kg per m³ × 9.81 m/s² × 550 m × 1,000,000 m³ ÷ 3.6 × 10¹² |
| Energy to lift 30,000 GL, no losses | 44,962 GWh a year | 30,000 × 1.50 GWh |
| With pump losses | 52,897 GWh a year | 44,962 ÷ 0.85 |
| Share of the solar output | 2.5% | 52,897 ÷ 2,102,400 GWh |
| Average pump power in the flood months | 12.1 GW | 52,897 GWh ÷ 4,380 hours |
Pipe and channel friction over the length of the corridors is not included, so the pumping energy is a lower figure than the real one.
Stored water is also the battery. Surplus solar pumps it to the upper reservoir by day; it runs back through turbines when power is needed.
One full discharge of the Alice Hub volume at the 400 m average head.
18% of the 16,000 GL. The water is reused each day.
| Quantity | Figure | How it is calculated |
|---|---|---|
| Energy in 1 GL at 400 m | 1.09 GWh | 1,000 × 9.81 × 400 × 1,000,000 ÷ 3.6 × 10¹² |
| Delivered by the turbines | 0.98 GWh per GL | 1.09 × 0.9 |
| 16,000 GL discharged once at 400 m | 15,696 GWh | 16,000 × 0.98 GWh |
| Half a day of output, one town | 19.2 GWh | 14,016 GWh ÷ 365 ÷ 2 |
| Water cycled for one town-night | 19.6 GL | 19.2 ÷ 0.98 GWh per GL |
| Water cycled for 150 towns | 2,936 GL | 150 × 19.6 GL |
| Nights carried by 16,000 GL with no refill | 5.5 | 15,696 ÷ 2,880 GWh a night |
The MMA Alice Hub memo uses an average head of 770 m for its seven gorge pairs and gives about 30,886 GWh usable.3 At 770 m the energy in 16,000 GL is 33,572 GWh before losses. This page uses the 400 m average across all storage locations.
| Item | Figure | Basis |
|---|---|---|
| Corridors | 7 | Seven MMA corridors |
| Towns | 150 | One every 100 km |
| Solar capacity | 1,000 GW | 6.7 GW a town; expandable in rings to 20 GW a town (3,000 GW) |
| Solar area | 40,000 km² | 40 km² per GW |
| Solar energy | ~2,102 TWh a year | 24% capacity factor; 7.4 times Australian generation in 2024 |
| Water harvested | 30,000 GL a year | MMA Memo 14 target |
| Energy to lift the water | ~53 TWh a year | 2.5% of the solar energy |
| Water stored | 16,000 GL | Alice Hub, MMA plan; range sites not yet sized |
| Battery, one full discharge | ~15,700 GWh | 400 m head, 90% efficiency |
| Water cycled each night | ~2,900 GL | Half of the daily solar output carried into the night |